JC Costs/Estimates by Project Manager
You can use the JC Costs/Estimates by Project Manager report to print Estimated Hours and Dollars, Actual Hours and Dollars and Balance Hours and Dollars to the Cost Type level of detail by selecting .
This report prints Estimated Hours and Dollars, Actual Hours and Dollars and Balance Hours and Dollars to the Cost Type level of detail. The report sorts by Company, Project Manager, Job, Phase and Cost Type.
|
Report Parameters |
Description |
|---|---|
|
Company |
Accept the default, or press F4 to select a company. |
|
Beginning Project Manager |
Select the Field Lookup button or press F4 to select the beginning project manager. |
|
Ending Project Manager |
Select the Field Lookup button or press F4 to select the ending project manager. |
|
Beginning Job |
Select the Field Lookup button or press F4 to select the beginning job. |
|
Ending Job |
Select the Field Lookup button or press F4 to select the ending job. |
|
Through Month |
Enter through month (MM/YY). |