Replace Topsoil in an Area
When you replace topsoil, you are lowering all the proposed grades within an area.
Because the topsoil replaced is not included in the cut or fill quantities, the amount of topsoil replaced can have a significant effect on the final calculated totals. For example, if you replace 6 inches of topsoil in a job site that requires fill, you will decrease the amount of fill required. If you replace 6 inches of topsoil in a job site that requires cut, you will increase the amount of cut required.
Additionally, any quantities of topsoil replaced will not be included in the export amount provided on the Summary tab. Replaced topsoil is tabulated separately. For more information, see View Total Quantities.
- Open a job in the Manage Earthwork Estimates screen.
- Select the Area tab, if it is not already active.
- In the Active Layer field on the toolbar, click
to select the Proposed layer.
- Click Select
on the speedbar.
- Select the area which you will use to replace topsoil.
- Click Prop
on the speedbar, or double-click within the area in question.
- In the Replace Topsoil field, enter the amount you want to replace.
- Click OK to save the topsoil replacing.