Snap a Line to an Existing Point, Line, or Area
-
Open a job in the Manage Earthwork Estimates
screen.
Note: To open a job in the Manage Earthwork Estimates screen, click Estimating > Earthwork > Manage Earthwork Estimates in the All Tasks pane. Click Open Existing Job. Then select the job you want to open, and click OK.
- Select the Takeoff tab, if it is not already active.
-
In the Active Layer field on the toolbar, click
to select the layer for which you want to digitize a line.
-
Click Snap
on the speedbar.
-
Click either the Point
or Trace
on the speedbar and digitize the new line.
-
When you are close to the item to which you want to snap the line, click Snap
on the speedbar to turn on snap.
- Click near the item to which you want to snap the line.
-
Click Snap
again to turn the snap tool off, or continue digitizing with the snap tool active, which will continue to snap the line to points, lines, or areas.
- Finish digitizing the line as needed.
-
Click Finished
on the speedbar.