File Layout for Historical Costs ASCII Files - Standard - Cost File Layout

The following is a description of which Spectrum fields will be included in the historical costs file:

Field

Description

1

Phase code

2

Job number

3

Phase description

4

Job completion date

5

Quantity (job-to-date)

6

Unit of measure

7

Area code (user-defined field specified on the starting screen)

8

Labor hours

9

Equipment hours (cost type #4 in Job Cost Installation)

10

Labor dollars

11

Material dollars

12

Subcontract dollars

13

Cost type #4 dollars

14

Cost type #5 dollars

15

User-defined cost type #6 dollars

16

User-defined cost type #7 dollars

17

User-defined cost type #8 dollars

18

User-defined cost type #9 dollars