Construction Partner Estimate Detail Export Add-in

Modified: 24 Sep 2026 B2W Estimate

Learn how to configure and export B2W Estimate data to generate files for import into Construction Partner.

Introduction

The following instructions walk you through an overview of the export, setting up default export options, configuring an estimate for export, and creating the file that you may then import to your Construction Partner accounting package.

Overview of the export

In a nutshell, the process of sending B2W Estimate information to your accounting package consists of creating an "export file" which contains information about your estimate's costs and prices. This file is saved in a format that will be imported and interpreted by your accounting system.

Of course, before you can successfully create this export file, you'll need to do some coding within certain fields at the item and/or cost component levels in your estimate. If you're thinking ahead (and if your codes are consistent) you can even do some "pre-emptive coding" within the Item Databases and Resources areas!

However, before we go into the details about cost codes, let's review some basics:

  • Default settings that tell B2W Estimate how to speak to your accounting package are stored in the Options dialog. This topic is discussed in the next section.
  • The export file that B2W Estimate generates contains information about the items in a specific estimate.
  • Both pay items and indirect items are exported.
    Note: Throughout this help topic, when "item" is used to reference a portion of B2W Estimate, it represents either a "pay item" or "indirect item". Otherwise, "pay item" or "indirect item" will be specified.
  • This export uses the bottom-up approach. This means that a child component with a cost code "overrides" its parent's cost code. More specifically, its costs are subtracted from its parent's, and it is exported as its own cost breakdown element.
  • For cost information to be exported, it must have a corresponding Construction Partner Phase Code. In B2W Estimate, Phase Codes are entered in an item's Job Cost ID field. Items with blank Phase Codes are not exported, and a warning is generated.
  • Construction Partner's Cost Codes are entered in B2W Estimate's Task JC ID fields for items. To export costs at the component level, you may instead enter the Cost Code in B2W Estimate's Job Cost ID field at the component level.
    Note: If the B2W Estimate item's Job Cost ID field is left blank, and the item has no child component with a value in its respective Job Cost ID field, a warning is generated.
  • Revenues and indirect items require both a Phase Code and a Cost Code; otherwise, they will not export.
  • Values for duplicate Phase Code/Cost Code combinations are not rolled-up together.
  • The export file contains up to six cost columns into which you can organize various cost categories. When multiple cost categories are assigned to the same column, the cost values are added together.

    Notes:

    • You may set your "Income" column to a unique, (i.e., non-shared), column number in order to keep pay item revenues in a separate column from costs. Regardless of column number assigned, since revenue is an "I" Type (income) record, it will export to a separate row from any "C" Type (cost) records.
    • If you plan to optionally break out Labor Burden and Equipment Burden using the Column Number setting in Options, be sure to give them column number values that are different than the ones assigned to 'Labor', 'Equipment Owned', and 'Equipment Rented'.
  • Suppressed items are always ignored when exporting to accounting.

Configuring your default export options

Before you can successfully export to Construction Partner, you must first configure some basic export settings in the Options dialog. This is part of the initial setup; once these settings are properly entered, you should not have to perform these steps again.

How?

  1. Launch B2W Estimate, and log in.
  2. Click Options in the Administration section on the Home Page or on the ribbon bar in an open estimate.
  3. In the Options dialog, click the Imports/Exports folder, then click the Export Settings page.
  4. In the Select Export Format box, select Construction Partner.
  5. Select the values that will be used as the Column Number for the required cost categories in the list.

    Figure 1. Example of Construction Partner options settings


    Fastpath:

    You may optionally select a column value for Labor Burden. Entering a value different from the one you're using for 'Labor' above will cause labor base and labor burden costs to be split out separately.

    You may optionally select a column value for Equipment Burden. Entering a value different from the one you're using for 'Equipment Owned' and 'Equipment Rented' above will cause equipment owned base, equipment rented base, and equipment burden costs to be split out separately.

    You may optionally enter values for Worker's Compensation Code, General Liability Code, and Change Request Code.
    Note: These values have no corresponding fields within B2W Estimate and are provided here so that you may populate them into the export file if necessary.

Configuring an estimate for export to Construction Partner

  1. Open the estimate that you wish to export to Construction Partner.
  2. On the Item Listing tab, enter a value for the Phase Code in the Job Cost ID field for each item in your estimate that you plan to export.

    Note:

    My Item Listing tab doesn't have a Job Cost ID column

    If you don't see a Job Cost ID column in your current Item Listing tab view, you may add it by going to View on the menu, select Customize Item Columns, click the Add... button, check the box for Job Cost ID, click OK, and then click OK.

    Note: You can also access the Job Cost ID field from the Estimate Detail tab, when you click on an item.

  3. To export costs at the item-level, enter the Cost Code values in each item's Task JC ID field. Otherwise, to export costs at the component-level, from the Estimate Detail tab, enter the Cost Code in the respective component's Job Cost ID field.

    Fastpath:

    My Item Listing tab doesn't have a Task JC ID column

    If you don't see a Task JC ID column in your current Item Listing tab view, you may add it by going to View on the menu, select Customize Item Columns, click the Add... button, check the box for Task JC ID, click OK, and then click OK.

    Fastpath:

    A recap of how B2W Estimate cost codes map to corresponding codes in Construction Partner

    The table below summarizes how to code items to generate costs, including indirects, and revenue records into the export file:

    Construction Partner's FieldsB2W Estimate's Fields
    Phase Code

    The value in the item's Job Cost ID field.

    Note: Items with blank Job Cost ID field values are not exported.

    Cost Code

    The value in the item's Task JC ID field for item-level exporting.

    The value in the cost component's Job Cost ID field for component-level exporting.

    The records will export along with any optional cost information as specified in the default export options.

  4. If you wish to code your estimate's indirect items, toggle the Item Type combo box to Indirect Items, and then enter values in the Job Cost ID and Task JC ID fields as described above.

Examples of common coding scenarios

Below are a few examples of different ways to code an item in an estimate. The screenshots were taken from B2W Estimate's Job Cost report, a useful tool when analyzing estimate cost coding.

Figure 2. Example 1: Exporting pay item level revenues and costs


Fastpath:

For pay item "201.1 - Clearing and Grubbing" above:

  • Revenue: Revenue will export to Phase Code "2800", the value in the Job Cost ID field, and Cost Code "100", the value in the Task JC ID field.
  • Costs: Costs will also export to Phase Code "2800", and to Cost Code "100", since there is no Cost Code values entered in any cost component beneath the item level.
  • Income and cost categories: Income and cost categories will export to one or more (up to six) columns as indicated in your default options settings.
Figure 3. Example 2: Exporting component level costs


Fastpath:

For pay item "201.1 - Clearing and Grubbing" above:

  • Revenue: Revenue will export to Phase Code "2800", the value in the Job Cost ID field, and Cost Code "100", the value in the Task JC ID field.
  • Costs: Costs will export to Phase Code "2800" and to each respective Cost Code as entered in the component level Job Cost ID fields. Based on this example, eight component level records will export (for Cost Codes "200" through "500").
    Note: The cost components under the "Grub" detail task will all summarize under Cost Code "200" since its children do not have Cost Codes.
  • Income and cost categories: Income and cost categories will export to one or more (up to six) columns as indicated in your default options settings.
Figure 4. Example 3: Exporting indirect costs


Fastpath:
  • Indirect item "200 - Project Trailer": It will export to Phase Code "5800", the value in the Job Cost ID field, and Cost Code "610", the value in the Task JC ID field.
  • Indirect item "300 - Project Supervision": Since the cost coding is at the "Foreman" component level, it will export to Phase Code "1400", the item's value in the Job Cost ID field, and to Cost Code "305", the value in its own Job Cost ID field.
  • Cost categories: For both of these indirect costs, cost categories will export to one or more (up to six) columns as indicated in your default options settings.

Creating the export file

Your final step is to create an export file that contains revenue and cost information for the items in your estimate. This file will then be imported into your accounting package.

How?

  1. Close any Microsoft Excel file that you may have opened during a previous export process. If this file is open, the export process will fail.
  2. Open the estimate that you wish to export to Construction Partner.
  3. Click the Tools menu, point to Import/Export, and then select Export Estimate Detail.
  4. The Export Estimate Detail wizard appears. Click Next.
  5. On the Select Export Format page, verify that Construction Partner is the selected export format, then click Next.
  6. On the Enter File Name page, click Browse, and navigate to the folder where you wish the export file to be created. The default filename will be the job title of your estimate with an Excel file extension. This is the file you will be importing into Construction Partner.
  7. Click Save, then click Next, then click Finish.
  8. Once the export program finishes, a dialog may appear to show you any warnings about missing codes. This does not mean the export failed. Review this information, then click Close.
  9. Import the Microsoft Excel file into Construction Partner.
Submit