What's New in B2W Estimate 19.2

Modified: 24 Sep 2026 B2W Estimate

What's New in B2W Estimate 19.2

Ability to show Markup % and Margin % on the Status Bar at the same time

The Status Bar Display options now allow both Markup % and Margin % to be displayed at the same time.

Resizable Estimate Check Wizard dialog

Both the Estimate Check Wizard and the Check Wizard Results dialogs are now resizable and the default width has been increased so that all options are fully readable without scrolling.

Hot Keys for the Estimate Navigation Menu

The navigation menu to move between the Estimating area, Subcontractor RFQ Management, and Vendor RFQ Management now includes hot key descriptions for one button access to each area.

Copy Indirect Item to Pay Items and vice versa

Indirect Items can now be copied and pasted back into the estimate as Pay Items (with the exception of Calculated Indirect Items). The same can be done with pasting a copy of a Pay Item as an Indirect item.

Send Bid Form and RFQ Notes to the top or bottom of the list

Notes on the Bid Form and RFQ Groups can now be sent directly to the top or bottom of the list with a single button select.

Darker shading for selected nodes on tree views

To make the currently selected node on the Estimate Detail Tree easier to see on monitors and projectors with less color contrast, the shading on the Estimate Tree View has been darkened when the node is selected but not highlighted.

Target Amount and Target Markup values shown on Bid Pricing Strategy Tab

The Bid Pricing Strategy tab includes two new columns for entering markup percentages for Indirects, Overhead, and Profit when any of those are specified as a percentage of a cost category. The new columns show the Target Amount of the markup category, and the Target Markup value based on the specified percentage.

Import/Export Work Type/Subtype when importing Pay Items

You can now specify Work Type and Work Subtype for each imported pay item. For exporting, each Pay Item's Work Type and Work Subtype is now included in the export file.

New "Cost/MH" column on the Item Pricing tab

This new column shows each item's cost per man hour within the item.

Show Total Crew Days on the Status Bar

The Total Crew Days in the estimate can now be displayed on the status bar.

Resizable "Add Items/Tasks" dialog in Cost Groups

The Add Items/Tasks dialog when adding members to a Cost Group can now be resized.

Expands All/Collapse All in Add WBS Levels dialog

The Add WBS Levels dialog now allows all levels to be expanded or collapsed with a single button select.

DBE Tracking based on current bid price

There is now an option to control whether DBE and other Minority Participation Tracking is calculated against the Target Bid Price or the Current Bid Price of the estimate.