Jobs — Activity tab
The Activity tab includes
To return the job list, click View Job List.
To access the Jobs — Activity tab, click Jobs on the navigation bar, select the job you want to view, and then click the Activity tab.
By default, the Date field is used to sort the field log, work log, and true-up list in chronological order. To sort the field log, work log, and true-up list differently, click a column header to sort your list in ascending or descending order based on the values within that column.
Getting started
- Date – The date on which the work was performed or a true-up was run.
- Activity ID – IDs are automatically assigned each time a new field log, work log, or true-up is created.
- Foreman/Employee – The foreman responsible for the field log or the employee associated with the work log.
- Supervisor – The supervisor responsible for the field log or work log.
- Status – The status — Approved, Rejected, Submitted, or Transferred — currently assigned to the field log or work log.
- Labor Hours – The total number of man hours recorded within the field log, work log, or true-up.
- Equip. Hours – The total number of equipment hours recorded within the field log, work log, or true-up.
- Labor Cost – The total labor cost as recorded within the field log, work log, or true-up.
- Equip. Cost – The total equipment cost as recorded within the field log, work log, or true-up.
- Mat. Cost – The total material cost as recorded within the field log or true-up.
- Trucking Cost –The total trucking cost as recorded within the field log or true-up.
- Sub. Cost – The total subcontracted cost as recorded within the field log or true-up.
- Misc. Cost – The total miscellaneous cost as recorded within the field log or true-up.
- Overall Cost – The sum of all costs recorded within the field log, work log, or true-up.
You have the option of filtering the Activity Summary and Activity list to show information for All, Production/Overhead, and Time & Material accounts.
- Select an option from the Show Information for Account Type list.
Use the column headers in the Activity section to sort the list by that column in ascending or descending order.
Working with field logs, work logs, and true-ups
To view details of a field log, work log, or true-up, select an Activity ID from the Activity list.
Field logs
Field logs are daily reports from the field that include information about work type, employees, subcontractors, and equipment and materials used. Attachments such as photos, plans, or other job-related documents can be added to field logs. Once submitted for approval, field logs are either approved or rejected by a supervisor or project manager, and may transferred to your accounting system.
- Click Create New Field Log.
- Complete the steps in the New Field Log Wizard.
- Select a field log Activity ID from the Activity list.
- Click Edit on the Field Log View page
- Edit field log information.
- Click Save & Close to save field log edits OR click Save & Continue Editing to save edits and continue editing.
- Select a field log Activity ID from the Activity list.
- Click Delete on the Field Log View page.
- Click OK to verify.
Work Logs
Work logs capture time for an individual employee's work on job tracking accounts, unpaid time, and equipment time.
- Select a work log Activity ID from the Activity list.
- Click Create New Work Log.
- Complete the steps in the New Work Log Wizard.
- Select a work log Activity ID from the Activity list.
- Click Edit on the Work Log View page
- Edit work log information.
- Click Save & Close to save work log edits OR click Save & Continue Editing to save edits and continue editing.
- Select a work log Activity ID from the Activity list.
- Click Delete on the Work Log View page.
- Click OK to verify.
True-ups
True-ups allow a user to adjust for:
- Cost differences that can accrue over time between estimated and average costs in B2W Track and actual costs in your accounting system.
- Quantity differences that can accrue over time for materials delivered and materials used in B2W Track and actual quantities in your accounting system.
The True-up add-in must be installed to see the Run a True-up button. See the Run/Import True-up section in About True-up for more help.
- Click Run a True-up at the top right of the Activity list.
- Select a true-up.
- Click
Edit. - Click
Save.
Only the most recent true-up on a job can be deleted.
- Select a true-up.
- Click Delete.