This page provides an overview of Assignments in B2W Schedule including:

For information on specific resource assignment types, select an option from the menu to the right under Assignments or an option under the Assignment types section of this page.

About Assignments

Assignments are scheduled resources for a specific date at a designated job site or place.

Use B2W Schedule to manage assignments for your resources. Assignments for different resource types display with different colors on the schedule. See Assignment types for more information.

To help you manage assignments, you can create custom schedule views in the Setup area. For example, you may have a schedule view for just crews by work type, or for employees by assignment location. See Creating schedule views for more information.

Assignment types

B2W Schedule allows you to schedule assignments for the following resource types:

Each type of resource assignment displays on the assignment grid with a different icon and color indicator. Assignments will always display with a background color on the assignment grid. Orders and Needs will display on the assignment grid with a colored border.

Depending on your currently selected schedule view, you may not see certain types of assignments. For example, if you view the All Equipment schedule on the assignment grid, you will see only equipment assignments on the assignment grid. You will not see employee assignments.

Common actions

This section includes common actions that can be performed with assignments in B2W Schedule.

Create assignment

For information on field definitions for specific resource assignments, see the respective help topic under Assignments in the topic menu at the top of this page.

You have 3 options for creating assignments:

  1. Click the New menu on the left of the window and select Assignment.
  2. Drag your cursor across one or more dates on the schedule and choose Create Assignment.
  3. Click on a resource or a date in its row and select Create Assignment.
Editing an assignment

Options for editing assignments vary depending on the type of resource and its context.

In most cases, clicking a resource assignment opens a menu that shows Edit with a submenu that lists the following options:

  • Edit Assignment
  • Unlink From Assignment (appears when an employee is linked to an equipment resource)
  • Relocate (Crew, Employee, Equipment)
  • Swap (Crew, Employee, Equipment)
  • Split Assignment
  • End Assignment

In other cases, the only option is to Edit the assignment, move assignment, or move order:

  • One-day assignments
  • Resources when they are part of a Transport Crew assigned to a move.
  • Move Assignments

In most cases, clicking a need opens a menu that shows Edit with a submenu that lists the following options:

  • Edit Need
  • Split Need
  • End Need

For information on field definitions for specific resource assignments, see the respective help topic under Assignments in the topic menu at the top of this page.

Copy or delete assignment

To perform either of these actions, select the assignment on the assignment grid and select Copy Assignment, or Delete Assignment.

For information on field definitions for specific resource assignments, see the respective help topic under Assignments in the topic menu at the top of this page.

View assignment on Map Panel

Click the assignment on the assignment grid and select View Assignment on the Map. The Map Panel will open displaying the location of the assignment and the assignment card docked in the panel.

Add resources to assignment

Only applies to production crew assignments.

Click the production crew on the assignment grid you want to add resources to, and select Add Resources to Assignment.

Split Assignment

You can split crew, employee, and equipment assignments that span multiple dates on the assignment grid.

To split an assignment in to 2 separate assignments:

  1. On the assignment grid, locate the assignment you need to split.
  2. Click the assignment on the date you want the split to begin and select Edit > Split Assignment.

The assignment will appear as two separate assignments on consecutive dates. The date you clicked will be the first day of newly created assignment.

End assignment

You can end crew, employee, and equipment assignments that span multiple dates on the assignment grid.

To end an assignment:

  1. On the assignment grid, locate the assignment you need to end.
  2. Click the assignment on the date you want it to end and select Edit > End Assignment.

The date you clicked and all dates after it will be removed from the assignment.

Complete move assignment

Click the move assignment on the assignment grid and select Mark as Complete. The move icon will change color to green to show that it has been completed.

Create substitution

Substitutions can only be created for employee assignments. See Create a substitution.