Use the Complete Work Order dialog box, accessed from either the Work Orders or Schedule pages, to record the details of the maintenance work performed on a work order.

Getting Started

To access the Work Orders or Schedule pages, click MAINTAIN on the navigation bar at the top of the B2W page and select either Work Orders or Schedule from the secondary navigation bar. You can also click the Maintain icon at the top left of any Maintain page and select Work Orders or Schedule from the menu that appears.

Note that Maintain is visible only to users who are associated with a Maintain Mechanic or Maintain Manager license and belong to a security role with appropriate permissions.

Learn more about assigning user licenses

Learn more about configuring security roles

Accessing the Complete Work Order Dialog Box

You can access the Complete Work Order dialog box from either the Work Orders or Schedules tab.

From the Work Orders Tab
  • Select a work order in the list pane of the Work Orders tab. The Details Pane will display the details of the work order.
  • At the top of the details pane, click Complete. This opens the Complete Work Order dialog box.
From the Schedule Tab
  • Select a work order in either the Unscheduled Work Orders or Scheduled Work Orders section of the details pane.
  • At the top of the corresponding section, click Complete. This opens the Complete Work Order dialog box.

Working with the Complete Work Order Dialog Box

What follows are descriptions of the elements of the Complete Work Order dialog box.

Note that the Complete Work Order dialog box is made up of two separate panels. On the first panel, the Completion Date and, if present, the Reading at Completion fields are required. They must be filled in before you can access the second panel.

None of the fields on the second panel of the dialog box are required. They may be blank or they may display selections made when the request or work order was created. You can edit them when you complete the work order.

Header
  • Top line of the header shows the work order number and the description.
  • Second line shows equipment ID and description.
Completion Date
  • The Completion Date field is filled with today's date. Edit as necessary.
  • Use M/D/YYYY format.
  • This field is required.
Notes
  • Add notes as needed in the Notes field.
  • Use the toolbar at the top of the Notes field as needed to format the text of your note.
Meter Readings at Completion
  • This element appears only if there are meters for this equipment.
  • The Reading at Completion field is required.
  • Meter entries consist of the following:
    • Meter - Name of the meter as defined in the Equipment tab for this piece of equipment.
    • Meter Type - Identifies what the meter is measuring, such as Hour Meter or Odometer.
    • Recent Reading Date - Date of the most recent reading.
    • Recent Reading - The meter value at the time of the most recent reading.
    • Reading at Completion - Required. The reading for the associated meter when the work order is completed.
  • Rules for entering meter readings:
    • A meter reading cannot be lower than the current meter reading.
    • A meter reading cannot be for a date previous to the current meter reading.
    • A meter reading cannot be for a date after the current date.
    • An hour meter reading cannot equal more than the number of hours that have elapsed since the current meter reading.

    The Completion Date field in the Complete Work Order dialog represents the meter reading date when the Complete Work Order dialog is saved.

Next Button
  • Click Next. to advance to the second panel.
  • The dialog box displays alerts if information is missing or improperly formatted.
Work Item Tabs
  • The dialog box displays a tab for each work item(s) included in the work order.
  • Each work order tab displays the following information:
    • The maintenance request number and description.
    • The reported hours for this work item, identified by a clock icon. This displays 00:00 until hours are reported.
    • The total reported quantity of parts for this work item, identified by the parts icon. This displays 0 until parts are reported.
Work Item Header
  • The header displays the ID generated and the description entered when the request was created.
Type
  • The type of maintenance task, specified when the request was created.
Problem Code
  • The mechanical symptoms that generated the request. Select from a drop-down list of possible problems.
Failure Code
  • Identifies the condition that caused the problem. Select from a drop-down list of possible failure conditions.
Action Code
  • The action taken by the mechanic to correct the problem. Select from a drop-down list of possible actions.
Component Code
  • Identifies a part or assembly within a piece of equipment. Begin typing to select a component code.
Hours
  • Displays the current reported and planned hours for the work item. This changes as planned and reported hours are added.
Planned Hours
  • Displays the estimated time required to perform the work; entered when the work order was created.
  • When Planned Hours have been added, the following columns appear:
    • Description - Summarizes the purpose of the planned hours.
    • Labor Type - Selected from the labor types listed in the Resources area.
    • Hours - The estimated number of hours needed to complete the specified task.
Add Planned Hours
  • Click to add planned hours.
  • See Adding Planned Hours, below.
Reported Hours
  • Reported Hours displays time already charged to the task through the work order or time cards.
Report Hours
  • Click to report hours spent on the work item.
  • See Reporting Hours, below.
Parts
  • Lists parts already added to the work item.
  • The parts list provides the following information:
    • Description - The part number and name.
    • Est Qty - The estimated quantity of this part; the number thought to be needed.
    • Rpt Qty - The reported quantity of this part; the number actually used.
    • Rpt Cost - The reported quantity times the price of the part as recorded in your database.
Add Parts
  • Click to add parts to the work item.
  • See adding parts, below.
Add Custom Parts
  • Click to add parts to the work item.
  • See adding parts, below.
Save Button
  • Click Save to confirm the completion of this work order.
  • You have two other options:
    • Click Previous to go back to the previous page if you need to change the date or the notes.
    • Click Cancel to close the dialog box and discard your changes.

Adding/Reporting Hours

The Complete Work Order dialog box displays planned and reported hours for each included work item. You can edit these elements.

Note that the Reported Hours section displays time already charged to the task through the work order or time cards.

Adding Planned Hours

Click Add Planned Hours to open the Planned Hours dialog within the work item. Complete the following fields:

  • Description - Summarizes the purpose of the hours reported.
  • Labor Type - Selected from the job titles listed in the Resources area.
  • Hours - The amount of time estimated to complete the work.

You can revise planned hours:

  • Click Edit to open a planned hours line item for editing.
  • Click Delete to delete a planned hours line item.
Reporting Hours

Click Report Hours to open the Report Hours dialog within the work item. Complete the following fields:

  • Description - Summarizes the purpose of the hours reported.
  • Employee - Selected from employees listed in the Resources area. Limited to only employees assigned the Mechanic role.
  • Labor Type - Selected from the job titles listed in the Resources area.
  • Date - The date the hours were worked. Enter in M/D/YYYY format.
  • Component Code - Identifies a part or assembly within a piece of equipment.
  • Start - The time of day the work started.
  • Stop - The time of day the work ended.
  • Regular Hours/Minutes - Hours worked that are eligible for regular pay. The time entry increment for minutes is defined under Business Units in the Settings area.
  • Overtime Hours/Minutes - Hours worked that are eligible for overtime pay. The time entry increment for minutes is defined under Business Units in the Settings area.

You can revise reported hours:

  • Click Edit to open a planned hours line item for editing.
  • Click Delete to delete a planned hours line item.

Adding/Editing Parts

Adding Parts

Click Add Parts to open the Add Parts dialog within the work item.

  • Select the parts you want to add. Note that when the dialog first opens, it lists all parts. There are three ways to filter the list:
    • Click the drop-down at the top of the dialog and select All Parts for Equipment to show only parts associated with the equipment on the current work order.
    • Use the search field above the list. Searching returns results for any part that has a matching string of text in the ID, Description, Category, and Subcategory columns.
    • Use the Scan UPC field to scan in a part's barcode using a UPC scanner. Note, the part must exist in the Parts resource and have a valid UPC code for the UPC scan to work.
  • Select the check box in the ID column for the parts you want to add to the work order, then click Next.
  • Specify an equipment code, estimated quantity (Est. Qty), and reported quantity (Rpt. Qty) as desired.
  • Click Save to add the selected parts to the work order. At this point there are two other options:
    • Click Previous to go back to the previous screen to make revisions.
    • Click Cancel to abandon the operation.

You can also add custom parts that are not included in your parts database.

Adding Custom Parts

Click Add Parts to open the Add Parts dialog within the work item.

  • Add any parts you need from your Parts database, as described above, then click Next.
  • Click Add Custom Part.
  • Complete the following required fields for each custom part: Description, Unit Cost, and unit of measure (UM).
  • Complete the following optional fields as needed: purchase order number (PO#), component code, estimated quantity (Est. Qty), and reported quantity (Rpt. Qty).
  • Click Save to add the selected parts to the work order. At this point there are two other options:
    • Click Previous to go back to the previous screen to make revisions.
    • Click Cancel to abandon the operation.

Note that a custom part is associated only with the work order in which you create it. If you plan to use a custom part again, you need to add it to your database on either the Parts page in the Resources area or the Parts page in the Maintain element.

Editing Parts

There are two types of edits you can perform on the parts list.

  • Click Delete to delete a parts line item.
  • Click Edit Quantities to open the Add Parts dialog within the work item to edit the equipment code, estimated quantity, or reported quantity.