Conflicts
Conflicts alert you to resources that have either been scheduled for two different assignments on the same date and time or have been assigned while unavailable due to certain events. For example, an employee may have been scheduled at a location assignment while also having a sick event for the same time and date. Conflicts can be managed directly on the schedule or by using the Conflicts Panel. Past conflicts are retained for 90 days.
To learn how conflicts appear on the Schedule and Map, see How Conflicts are displayed.
Getting started
Conflicts appear on both the schedule view and the map.
Schedule
On a schedule view, the Conflict Notification icon
will appear next to the resource in conflict. A Conflict and Need Notification icon on the date header could signify that a conflict is taking place within that timeframe.
The Conflict and Need notification icon
at times may indicate unfilled orders/needs and may not always indicate that there are conflicts associated with a date.
Map
The Conflict Notification icon
indicates conflicts in location cards that appear in the docking area on the Map Panel.
You can open the Conflicts Panel from four places:
- Click the Conflicts Panel button
. This will display a list of conflicts for your current schedule view — including any filters, date selections, and search criteria you have set. - Click the Conflict Notification icon next to a resource on the schedule view OR map
and select View in Conflicts Panel. - Click the Conflict and Need Notification icon next to a date on the schedule
and select View in Conflicts Panel.
You can search and sort the conflicts panel to find a specific conflict or narrow down the list of conflicts.
To search
Enter a search term in the Search field at the top of the conflicts panel. The list of conflicts filters as you type.
To filter
Use the filter button to narrow the list of all conflicts when more than one conflict type exists. Select All, Production Crew, Equipment, or Employee.
Employees
- Scheduled at two location assignments
- Scheduled for two crew assignments
- Schedule for a location assignment and crew assignment
- Schedule for a location assignment or crew assignment and a sick day or vacation event
Equipment
- Scheduled at two location assignments
- Schedule for a location assignment and crew assignment
- Schedule for a location assignment or crew assignment and a Down for Maintenance or Scheduled Maintenance event
- Schedule for a location assignment or crew assignment and move assignment
Production Crews
- Scheduled at two locations assignments
- Equipment or Employee within the crew is experiencing any of the crew assignment conflicts listed above
Internal Truck
- Equipment or Employee within the truck is experiencing any of the conflicts listed above
Working with conflicts
Sometimes it is more efficient to manage conflicts directly on your schedule view. This can be useful when resolving small conflicts — such as an employee assigned to the same dates and times at two different locations.
Resolve conflicts directly on the schedule
- Drag a conflict and drop it next to an appropriate available resource and date:
Use the Conflicts Panel to find and resolve conflicts. The conflicts that appear in the Conflicts Panel are based on the selected dates and filters currently applied to your schedule view and are sorted first by date (earliest to latest), and then by resource name (alpha-numerically).
An icon-based filter control appears at the top of the panel when more than one type of resource is shown on the schedule view. Select an icon to filter the list of conflicts by that resource (default is All). The search field can also be used to locate a specific conflict or to filter the number of conflicts in the panel that match the entered text.
When you select a conflict from the Panel, the conflict appears on your schedule view with available resources to resolve the conflict.
From here you can:
- Drag the assignment or need to a specific resource type that will resolve the conflict.
- Use the Resolve with menu to see if another resource type can resolve the conflict.
Conflicts Panel tips
- Use the Search bar within the Conflicts Panel to search for specific conflicts. Search by for employees, equipment, or crews by name or number.
- Set Filters on your schedule view to show fewer resources which also reduces the number of conflicts displayed in the panel.