Mass Haul Planner captures mass haul material orders that are internally dispatched as well as truck only orders. Use Mass Haul Planner to assign and manage these orders and trucks or trucking organizations which have been assigned to them.

Getting Started

Accessing the Mass Haul Planner

To access Mass Haul Planner, click Schedule on the B2W navigation bar then click the Mass Haul Planner tab.

Selecting a date

The Mass Haul Planner displays one day at a time. You can change the date to view past moves and to plan future moves.

When you navigate to the Mass Haul Planner, it shows the current day at the top left of the page.

  • Click the arrows (Previous Day or Next Day) on either side of the date to change the view one day at a time.
  • Click the date to access a calendar menu.
    • Type a date in the date field at the top of the calendar menu.
    • Select a date on the calendar.
    • Click the arrows (Previous Month or Next Month) on either side of the month to page through the calendar.
Colored status codes

The left edge of every order card is colored to show its status.

  • Unassigned (Blue): No trucks have been assigned.
  • Planned (Light Purple): A subcontracted truck or trucking organization has been assigned but not confirmed.
  • Confirmed (Yellow): All trucks or trucking organizations have confirmed.
  • Complete (Green): The order has been completed.
Column definitions

The Mass Haul Planner grid provides information for each mass haul assignment and displays the following columns:

  • Source – Where the trucks are to be loaded.
  • Load Time – The time that the trucks are expected to arrive at the source.
  • Duration – Time Duration (hours).
  • Duration – Length of the assignment (hours).
  • Trucks – Lists the number of requested, planned, and confirmed trucks.
  • Truck Type – Specify which type of truck to use. The field will show a list of truck types that can transport materials. Truck types are set up in the Resources area, under Equipment Types.
  • Truck Type – Which types of truck were specified for the order.
  • Material – Material that was requested.
  • Quantity – How much material was requested.
  • Destination – Where the trucks are going after they are loaded.
  • On-Site Time – The when the trucks are expected to arrive at the destination.
  • On-Site Time – When the trucks are expected to arrive at the destination.
  • Requested By – The person making the mass haul request.
  • Customer Contact– Contact from the customer organization and their phone number.
  • Truck Notes – You can type additional information not covered by the other fields in this dialog.
  • Production Crew – Production crew associated with the order.
  • Tracking Account / Accounting Reference – Job's tracking account or customer accounting reference associated with the order.
Applying Filters

Click Filters to access the Filter menu. Use the Filters menu to select filters (Business Unit, Orders For, Source, etc.) and then instances. For example, if you select the Source filter and then add a specific source, the mass haul planner shows only orders and assignments for the selected source. The Filters button appears blue when filters are applied.

To remove filters, click Clear Filters, then Apply.

Managing columns

You can change the order of columns and remove certain columns in the Manage Columns dialog box. To open the Manage Columns dialog box, click Options at the top right of the screen and select Manage Columns.

You can customize your view of the Mass Haul Planner by rearranging the columns. To do this:

  • Click Options at the top right of the screen and select Manage Columns. This opens the Manage Columns dialog.

Use this dialog to change the order of columns and remove certain columns, as described below.

Change order of columns

In the Manage Columns dialog box, drag and drop the column names into the desired order. The top name will be the first column.

In the Manage Columns dialog box, drag and drop the column names into the desired order. The top name will be the first column at the left of the grid.

Remove columns

Certain columns can be removed to simplify the Mass Haul Planner view. To remove columns:

  1. Open the Manage Columns dialog box and click the remove icon next to the columns you want to hide from view. Once removed, the column will appear at the bottom of the list under the Hidden columns header and will also be hidden from the Mass Haul Planner grid. To add the column back, click the add icon next to the column name and it will reappear on the grid.

Load Time, Source, Truck Type, Trucks, and Destination are required columns and cannot be removed.

  1. Click Apply to save changes. Once removed, the column will appear at the bottom of the list under the Hidden columns header and will also be hidden from the Mass Haul Planner grid. To add the column back, click the green add icon next to the column name and it will reappear on the grid.

Load Time, Source, Truck Type, Trucks, and Destination are required columns and cannot be removed.

Mass Haul Planner alert icons

The following alert icons appear on assignments in the Mass Haul Planner grid. You can click the icon on the grid to display a tooltip that explains the warning, conflict, or error.

Icon Description Details
Warning
  • Indicates that an order has been modified after trucks have been assigned but no immediate action is needed.
Conflict
  • Indicates that assigned trucks have other conflicting assignments in the system.

Error

  • Indicates that an order with trucks already assigned has been rescheduled, relocated, or deleted.

Working with Assignments

Assign Trucks

Unassigned orders are blue and represent trucking requests that do not yet have trucks assigned. To assign trucks for unassigned trucking jobs:

  1. Click on the trucking request or click on the options menu on the left side of the trucking request and select Assign Trucks. The Assign Trucks page opens. Before you create an assignment, determine the type of resource suitable for the assignment and the quantity of resources that will be required to complete the assignment.
  2. Click on the trucking request or click the arrow symbol () on the left side of the trucking request and select Assign Trucks from the options menu. The Assign Trucks page opens. Before you create an assignment, determine the type of resource suitable for the assignment and the quantity of resources that will be required to complete the assignment.
  3. Review the General Information section which displays the following:
    • Material and amount (material orders only)
    • Start time or load time
    • On-site time
    • Number of trucks and duration
    • Name of person making the request
    • Edit Order – Click if you need to change this information.
  4. Select trucks from truck list on the right side of the screen. Each truck entry will display its name and ID, Truck Type, and whether it is internal or a subcontracted truck. Use the following options to narrow the results:
    • Find By – Use the Find By menu to display all trucks, subcontracted, or brokered trucks. By default, Truck is selected which displays all trucks.
    • Search – Use the search field to find a specific truck or truck type. The list of trucks filters as you type.
    • Truck Type – Filter the available list of trucks by type. Click in the Truck Type field to display a list of truck types. Select a type to view trucks it that category.
  5. After selecting the check box beside the trucks you want to assign, click Add To Assignment.
  6. Review the trucking details to verify the start time, truck, driver, type, and capacity for the assignment. Optionally, add details for:
    • Route URL (material orders only) – Paste the URL from an online map service that provides directions from the source to the destination associated with the material order.
    • Truck Notes – Add any information useful for the assignment. This will appear in the Truck Notes column of the Mass Haul Planner page.
  7. Click Assign Trucks. The Mass Haul Planner page will open, displaying the trucking request as either:
    • Planned (Light Purple): A subcontracted truck or trucking organization has been assigned but not confirmed.
    • Confirmed (Yellow): All trucks or trucking organizations have been confirmed.
Trucking Details

The Trucking Details area appears in the following dialogs:

  • Modify Mass Haul Assignments
  • Assign Trucks

This area displays the following fields:

  • Route URL (material orders only) – Paste the URL from an online map service that provides directions from the source to the destination associated with the material order.
  • Truck Notes – Add any information useful for the assignment. This will appear in the Truck Notes column of the Mass Haul Planner page.
To revise the spacing and default start time
  1. Click Edit Start Time and Spacing on the Spacing & Default Start Time line and change the following as needed:
    • Number of trucks per interval (Type a new number in the field.)
    • Interval, in minutes (Type a new number in the field.)
    • Start time (Type a new time in the field. You can also click to select a new time from a menu.)
  2. Click Apply to make the changes or Cancel to close the dialog without changes.
To change an individual Start Time
  • Click in the Start Time field for a truck and type a new time. You can also click to select a new time from a menu.
  • This has no affect on the Start Time for other listed trucks.
To reassign a truck to a different start time
  • Drag an assignment up or down the list of assigned trucks to the desired start time.
To Edit a Truck Assignment
  1. Click an assignment in the Trucking Details section. This opens the Edit Truck Assignment dialog at the right side of the Mass Haul Planner.
  2. Edit the following as needed:
    • Truck – Begin typing the name of a truck that begins to the organization of the currently assigned truck and select a new truck from the list.
    • Edit Truck – Click to open a dialog for editing the following:
      • Driver – Appears for both internal and subcontracted assignments. Delete the current driver and begin typing the name of the replacement. A menu lists available replacements from either the subcontractor or the internal employee resources.
      • Equipment – Appears only for internal assignments. Click in the field to show a list of available equipment resources. Add equipment as needed.
    • Capacity – Edit to change the capacity of the selected truck.
    • Empty On-site – Select this check box to indicate that the truck should arrive empty.
    • Confirm – Available for subcontracted trucks only. Select to confirm or clear to unconfirm the truck for the current assignment.
    • Driver Notes – Add comments specifically for the assigned driver. These notes will be included in the email and text message notifications that are sent to drivers.
  3. Click Apply to accept your changes or Cancel to discard them.
Delete a truck assignment
  1. Click the arrow symbol () on the left side of a trucks only order and select Unassign Trucks from the menu. This opens the Unassign Trucks dialog.
    • The dialog lists all the trucks assigned to the order.
  2. Click Unassign to remove all the listed trucks from the assignment or Cancel to close the dialog without changes.
Confirm Trucks

Follow these steps to confirm truck orders in the Mass Haul Planner:

  1. Click Confirm Trucks in the Mass Haul Planner.
  2. The Confirm Trucks dialog opens. It shows a list of subcontractors or brokers with assignments that have not been confirmed. Select a subcontractor or broker to begin confirming assignments.
  3. The right side pane shows all unconfirmed truck orders for the selected subcontractor or broker. The orders are listed by start time then by destination.
  4. You can do the following:
    • To confirm all truck orders for a destination, select the check box on the gray header.
    • To confirm a single truck order, select the check box for that line.
    • To select a different truck to fill the order, click in the Truck field and type the name of a different truck template for the subcontractor or broker.
    • Click Edit to open the Edit Truck Assignment Dialog.
      • See Edit a truck assignment, below.

    • Click Delete to delete the truck order.
  5. When you are finished selecting, editing, or deleting, click Save and Confirm. This closes the detail pane. Subcontractors or brokers remain in the Confirm Trucks list until all orders are confirmed or deleted.
  6. Click Return to Mass Haul Planner when finished.
Swap a truck assignment

When you edit a truck assignment, you can also swap the assignment. By swapping, you can assign a different type of truck from a different subcontractor or broker.

  1. Click an assignment in the Trucking Details section. This opens the Edit Truck Assignment dialog.
  2. In the Edit Truck Assignment dialog, click Swap Assignment. This opens the Swap Truck Assignment dialog.
  3. Use the fields at the top of the dialog to identify the truck to swap.
    • Find By – Choose Truck, Subcontractor, or Broker.
    • Search – Appears when you select Truck in the Find By list. Type letters and numbers contained in the information about the truck you want to find.
    • Subcontractor – Appears when you select Subcontractor in the Find By list. Begin typing to select a subcontractor. Available subcontractor choices vary depending on the selected truck type.
    • Broker – Appears when you select Broker in the Find By list. Begin typing to select a broker. Available broker choices vary depending on the selected truck type.
    • Truck Type – Click in this field and select from the list of available truck types.
    • Filters – Appears when you select Truck in the Find By list. Click to open the Filter dialog.
  4. Select a truck from the list.
  5. Click Swap Assignment to swap the assignment or Cancel Swap to close the dialog and discard the swap.
Unassign Trucks

To unassign trucks from an order:

  1. Click the arrow symbol () on the left side of an order and select Unassign Trucks from the options menu. This opens the Unassign Trucks dialog.
    • The dialog lists all the trucks assigned to the order.
  2. Click Unassign to remove all the listed trucks from the assignment or Cancel to close the dialog without changes.

In some cases, Unassign Trucks is the only operation you can perform on an order. These orders are shaded gray and are marked with an alert icon (). You can click the alert icon to view a tool tip that describes the status of the order. To open the Unassign Trucks dialog, click anywhere on the order and complete the operation as described above.

Edit Trucks Only Orders

To edit trucks only orders on the Mass Haul Planner:

  1. Click the options menu next to the trucking order you want to edit.
  2. Click the arrow symbol () on the left side of the trucking order you want to edit.
  3. Select Edit Trucks Only Order.
  4. Modify the truck details and click Apply.
  5. Click Save.
Edit Materials Orders

To edit material orders on the Mass Haul Planner:

  1. Click the options menu next to the material order you want to edit.
  2. Click the arrow symbol () on the left side of the material order you want to edit.
  3. Select Edit Material Order. The Edit Material Order page opens.
  4. Modify the Mass Haul Details section and click Apply.
  5. Click Save.
Modify Assignments

To change the trucks assigned to a trucking assignment:

  1. Click the trucking assignment you want to modify. The Modify Mass Haul Assignments page opens.
    • You can also click the options menu beside the trucking assignment you want to modify and select Modify Assignments.
  2. Use the fields at the top of the dialog to select other trucks for the assignment.
    • Find By – Choose Truck, Subcontractor, or Broker.
    • Search – Appears when you select Truck in the Find By list. Type letters and numbers contained in the information about the truck you want to find.
    • Subcontractor – Appears when you select Subcontractor in the Find By list. Begin typing to select a subcontractor. Available subcontractor choices vary depending on the selected truck type.
    • Broker – Appears when you select Broker in the Find By list. Begin typing to select a broker. Available broker choices vary depending on the selected truck type.
    • Truck Type – Click in this field and select from the list of available truck types.
    • Filters – Appears when you select Truck in the Find By list. Click to open the Filter dialog.
  3. To delete assigned trucks, click Delete beside the truck in the Trucking details section.
  4. When you are finished selecting trucks, click Add To Assignment.
  5. Click Save under Trucking Details to update the assignment and return to the Mass Haul Planner page.
The New menu

The New menu is located at the right side of the Move Planner header

  1. Click New to create:
    • Crew Assignment
    • Crew Need
    • Production Target
    • Material Order
    • Trucks Only Order
    • Event
      • Employee
      • Equipment
      • Location
    • Move Order
    • Move Assignment
  2. The corresponding dialog opens. Enter all required information to complete the creation.

Notifications

Use the Send Notifications panel to send email, text messages, or both, to drivers about their upcoming assignments. These automatically created notifications list all scheduled pickups and drop-offs for the assigned transport crews and trucks.

Security role settings determine your access to Send Move Alerts features. Some users may not be able to send move alerts.

Send Notifications

Follow these steps to send notifications from the Mass Haul Planner:

  1. Click Send Notifications to send notifications to designated contacts for a subcontractor or broker. This opens the Send Notifications dialog.
  2. Select either the Planned or Confirmed view.
    • Select Planned to view the subcontractors or brokers who have unconfirmed truck only orders.
    • Select Confirmed to view individual orders.
  3. Specify the notifications to be sent.
    • Select New and updated schedules to send notifications only for new truck only orders or orders that have been changed.
    • Select All scheduled to send notifications to all scheduled truck only orders.
  4. Select check boxes to indicate which contacts should be notified and how to notify the contacts (email, text message, or both).
  5. When all selections have been completed, click Send. Messages will be sent per the selections made in this dialog.
    • Dispatchers receive notifications of all assignments.
    • Truck drivers receive notifications of their assignments.
Email Preview

You can preview notifications before you send them to individual recipients.

  • Click Email Preview.

This combines all current notifications into one email and sends it to the email address associated with the current user.

Notification Method

Under Notification Method, the following appears for each listed or truck:

  • Internal (without a dispatcher name) for owned trucks.
  • Organization name for subcontracted trucks.
  • Dispatcher names for the subcontractor.
  • Truck name.
  • Driver for the selected truck.
  • Check boxes for email and text message.

Select the email, text message, or both check boxes to specify how a driver will be notified.

Some trucks and internal transport crews will not have drivers; some subcontracted transport crews or will not have a crew contact. In such cases, No contact appears in place of a name and the email and text message check boxes are disabled.