Introduction

A material order is a request to move a quantity of a material from one location to another. Material orders appear in Schedule on the assignment grid, Location Overview, and Mass Haul Planner.

Permission settings for working with Material Orders

To work with Material Orders, you need the appropriate permissions which are set on the Security Roles page in the Setup area. There are Create, View, Edit and Delete permissions for both Internal Material Orders and Customer Material Orders. These selections appear in the Schedule area of the Security Role View and Security Role Edit pages.

Learn about security role permission settings

Assignment grid

For material orders to show on the assignment grid and on location cards opened from the assignment grid, the schedule view needs to include Materials and Material orders.

Learn about creating schedule views that will show material orders

Location Overview

On the Location Overview, location cards will always show material orders associated with a location on the selected day.

Move Planner

Move Planner always shows delivery and internally dispatched material orders.

Mass Haul Planner

Mass Haul Planner always shows mass haul and internally dispatched material orders.

Getting Started

Creating material orders from the New menu

You can create material orders from the New menu, which appears in these places:

  • Assignment grid, any schedule view
  • Location Overview
  • Move Planner
  • Mass Haul Planner

To create an order:

  • Click New and select Material Order

This opens the New Material Order dialog. You can create either internal or customer material orders.

Creating material orders from the assignment grid

You can click on various parts of the assignment grid to open a menu that includes Create Material Order. The format of the current schedule view determines whether or not this command appears.

  • Customer Listing — When an assignment grid shows a schedule view is set up with the Customer Listing format, you can click anywhere on any row to create a material order for that customer.
  • Job Sites & Places — Click on a job site or place in the list column of the schedule view. Material orders are listed under the site or place.
  • Production Crews — Material is listed under the crew and is visible when you expand the crew. Material orders linked to a production crew will only appear on crew schedule views.
  • Materials — Click on any blank space in rows that list materials.

Learn more about schedule formats

Order types

You can create ten different types of orders by selecting different options on the New Material Order pre-check page. You need to provide different information for each order type.

Internal

There are six different types of internal material orders:

  • Mass Haul Drop-off, Internally Dispatched
  • Mass Haul Removal, Internally Dispatched
  • Mass Haul Drop-off, Vendor Dispatched
  • Delivery Drop-off, Internally Dispatched
  • Delivery Removal, Internally Dispatched
  • Delivery Drop-off, Vendor Dispatched
Customer

There are four different types of customer material orders:

  • Mass Haul, Internally Dispatched
  • Mass Haul, Pickup by Customer
  • Delivery, Internally Dispatched
  • Delivery, Pickup by Customer

Material Order field definitions

New Material Order pre-check page

Start your material order here. These selections will define the order type.

Material Needed For

  • Internal — Ordered from within your business.
  • Customer — Ordered for a customer organization.

Order Type (Not available if you select Customer under Material Needed For.)

  • Material Drop-off — Delivering materials to a job site or place.
  • Material Removal — Picking up materials from a job site or place.

Transport Type

  • Mass Haul — Used when ordering materials to be moved at a rate, such as for asphalt installation, milling or aggregate removal.
  • Delivery — Used when ordering materials to be moved within a time frame, such as a load of sand needed on-site by the end of the week between 6:00 AM and 4:00 PM.

Truck Responsibility (Not available if you select Material Removal under Order Type.)

  • Internally Dispatched — Your business will arrange the trucking for this material.
  • Vendor Dispatched — The material supplier will arrange the trucking for this material.
General information page

The header on this page shows the type of order (such as Delivery Drop-off, Internally Dispatched). It has the following fields:

  • Job Site/Place — (Internal orders only) The material will be delivered to or removed from this location. Job Sites are defined in the Jobs area; Places are defined in the Resources area.
  • Customer — (Customer orders only) The company receiving the materials. Use Organizations in the Resources area to define customers.
  • Tracking Account — (Internal orders) Items you want to track within a job. Shows accounts in use at the location you selected.
  • Accounting Reference — (Customer orders) Typically a reference used by customers to track items within a quote.
  • Customer Contact — (Customer orders) A representative of the customer. Contacts are set up in the Resources area, on the Organization View page for the customer organization.
  • Requested By — An employee in your business.
  • Material — What will be delivered. Begin typing to select a material or click Select Material and use the Select Material panel.
  • Quantity — How much material will be delivered.
  • Relocate with Crew — (Internal orders) When selected, the material order will be associated with the crew. If the crew is relocated, the material order will be relocated with it.
  • Source — Where the material will be picked up. Begin typing to select a source or click Select Source and use the Select Source panel.
  • Destination — Where the material will be delivered.
  • Material Notes — You can type additional information not covered by the other fields in this dialog.
Editing the general information

There are three places where you can edit read-only information on the General Information page.

  • Edit Order Type — Clicking Edit takes you to the material order pre-check page.
  • Source: Edit Address or Coordinates — Click Edit to open a dialog where you can change the address or type a GPS location.
  • Destination: Edit Address or Coordinates — Click Edit to open a dialog where you can change the address or type a GPS location.
Delivery details
  • Dates — To change the dates, click Edit to open a calendar dialog.
  • Earliest Time — Earliest time to deliver the material. Type the time or click the clock and select a time from the menu.
  • Latest Time — Latest time to deliver the material. Type the time or click the clock and select a time from the menu.
  • Production Crew — (For internal orders only.) Associate a material order with a production crew.
  • Truck Type — Specify which type of truck to use. The field will show a list of truck types that can transport materials. Truck types are set up in the Resources area, under Equipment Types.
  • Truck Notes — Type in comments, instructions, and so on, regarding the delivery details.
Mass Haul details

Use this panel when Mass Haul is the Transport Type.

  • Date — Date of the mass haul.
  • Load Time — The time that the first truck is to be loaded with material.
  • On-Site Time — Internally Dispatched only. When the first truck is expected on-site to be unloaded.
  • Quantity — How much material will be delivered.
  • Duration — Amount of time needed to move the total daily quantity from source to the destination.
  • Production Rate — The quantity divided by the duration.
  • Production Crew — (For internal orders only.) Associate a material order with a production crew.
  • # of Trucks — Appears when you select # of Trucks. This is the total number of trucks required to move the total quantity from source to destination.
  • Truck Rate — Appears when you select Truck Rate. This is the capacity of all trucks for a given round.
  • Spacing — Amount of time between deliveries.
  • Truck Type — Specify which type of truck to use. The field will show a list of truck types that can transport materials. Truck types are set up in the Resources area, under Equipment Types.
  • Route URL — Paste the URL from an online map service that provides directions from the source to the destination associated with the material order.
  • Truck Notes — Type in comments, instructions, and so on, regarding the delivery details.
Select Material
  • Filter by Category — Click in this field, then type the name of a category or select a category from the list. You can select multiple categories.
  • Search — Begin typing. As you type, materials that don't match your search are removed from the list. Your search will find occurrences in all columns.
  • All, Permanent, Temporary — Select to list All, or Permanent, or Temporary materials. The Temporary attribute is linked to a material under Resources > Materials.
  • Add Material to Order — Click to add the material and clear the panel.
Select Source
  • Filter by — Click in this field and select a filter from the menu.
  • Vendor — (Internal orders.) Click in this field, then type the name of a vendor or select a vendor from the list.
  • Search — Begin typing. As you type, locations that don't match your search are removed from the list. Your search will find occurrences in all columns.
  • Add Source to Order — Click to add the source location and clear the panel.

Working with Material Orders

Material Order Status
  • Requested: Orders without a source or destination for the material.
  • Open/Unassigned (Blue): Orders without any trucks or transport crews assigned to transport the material.
  • Open/Submitted (Purple): Orders that do not need any trucks or transport crews assigned but have not been received.
  • Planned (Light Purple): Orders with trucks or transport crews assigned but not confirmed.
  • Confirmed (Yellow): Orders with trucks or transport crews assigned and all confirmed Or materials received but not yet completed.
  • Complete (Green): The order has been completed.

On the assignment grid, requested material orders are white with a brown outline. Open, Planned, and Complete material orders are light brown with a brown outline.

Select a location

Follow these instructions to add the missing source or destination to a Requested material order.

  1. Click on a Requested material order on the assignment grid or on a location card. The available commands in the menu will vary depending on what's missing from the order.
    • Clicking Select a Location opens the Select Location dialog.
  2. Use the following fields to select a source or destination for the order:
    • Filter by — Click in this field and select a filter from the menu.
    • Vendor — (Internal orders.) Click in this field, then type the name of a vendor or select a vendor from the list.
    • Search — Begin typing. As you type, locations that don't match your search are removed from the list. Your search will find occurrences in all columns.
  3. Click Save to confirm your selection.
Editing an order
  1. Click on a material order in any status and select Edit Material Order. This opens the Edit Customer Material Order or Edit Internal Material Order dialog.
  2. Edit as needed.
    • Some information, such as General Information, Source and Destination addresses, and Dates, needs to be edited in a dialog. To open the dialog, click Edit next to the information you want to change.
  3. Click Save, Apply, Update Mass Haul Details, or Cancel as needed.
Push Order

Push Order

Use the Push Order command when you need to call off work for a day or more due to unexpected events, such as inclement weather.

Specific security settings required: To use the Push Order command, you need a security role that includes the following permissions: View and Edit for Trucks Only Order.

Follow these steps:

  1. On the assignment grid of the Schedule Listing view, find the order you need to push. Click the order on the date you need to cancel. This displays a menu.
  2. On the menu, click Edit to expand a submenu. In the submenu, click Push Order. This opens the Push Order dialog.
  3. In the Push to Date field, type the date you want to restart work.
    • You can also click the icon to open a calendar menu for selecting the date.
  4. In the Include Non-Working Days checklist, select any non-working days that you want to re-classify as working days for the duration of the push.

    Include Non-Working Days appears only when the location of the order has non-working days. For more information, see About Non-Working Days, below.

  5. Click Save to apply your changes or Cancel to discard them.
About Non-Working Days

When the locations include scheduled non-working days, an additional section appears in the dialog:

  • Include Non-Working Days – Shows a checklist of the location's planned non-working days.
    • Leave the checkboxes clear to keep these as non-working days.
    • Select the checkbox for any day that you want to include as a working day in the pushed order.

By including non-working days, you can make up the time to avoid or minimize impact on the assignment's end date.

Copying an order
  1. Click on a material order in any status and select Copy Material Order. This opens the Copy Customer Material Order or Copy Internal Material Order dialog.
  2. The dialog displays the same information contained in the original order. Edit as needed.
    • Some information, such as General Information, Source and Destination addresses, and Dates, needs to be edited in a dialog. To open the dialog, click Edit next to the information you want to change.
  3. Click Save, Apply, Edit Mass Haul Details, Create Material Order, or Cancel as needed.
Receiving materials
  1. Click on a material order that is either Open or Planned and select Receive Material. This opens the Receive Material dialog which shows the following:
    • Date — Default: Date selected on the assignment grid or from location card.
    • Received Quantity — Default: Remaining quantity from the order.
    • Received By — For customer orders, blank or Customer Contact, if specified. For internal orders, blank or Requested By employee if specified.
    • Remaining Quantity — Total quantity minus received quantity.
    • Mark order complete — Default: selected
  2. Complete the dialog.
    • Date — Edit as needed.
    • Received Quantity — Edit as needed. The dialog shows a message if you type a quantity less than the ordered quantity.
    • Received By — (Optional) Type a name. For internal orders, you can select from names listed under Resources > Employees. For customer orders, you can select from names listed under Resources > Organizations > Contacts for that customer.
    • Remaining Quantity — Automatically calculated: Order quantity minus received quantity.
    • Mark order complete — Leave selected or clear as needed. Clearing this check box will clear the message described above.
  3. Click Save or Cancel to close the dialog.

Learn about Employee resources.

Learn about Contacts in Organizations.

Deleting an order

To delete a material order:

  1. Click on a material request or order in any status and select Delete Material Order. This opens the Confirm Delete dialog.
  2. Click Delete or Cancel to close the dialog.
    • The dialog shows an alert if any material has been received against the order. Deleting the order will also delete the transactions for the material that has been received.
Marking as incomplete (for completed orders only)
  1. Click on a completed material order and select Mark as Incomplete.
  2. The order status changes immediately, from Completed ( ) to Planned ( ).