Material Production
Material Production displays material orders sourced from Places that produce materials. Use the Material Production page to review daily totals for a given week, over capacity warnings, and material totals by locations.
Getting Started
To access the Material Production tab, click Schedule on the B2W navigation bar then click Material Production.
For a Place to appear on the Material Production page, configure it with the following properties:
- Produces Material – (Required) must be selected.
- Production UM – (Required) set to either weight/HR or volume/HR.
- Production Capacity – (Optional) can also be set to alert users when this number is exceeded.
The Material Production page includes three views that use the same order information. All views share the same filters, which control the locations and orders shown. Search behavior varies depending on the specific information in each view.
Use the view selector buttons at the top left of the page to toggle between
- Order View – See orders sourced by their locations.
- Material Demand – See total quantities for each material sourced at their location. You can also identify orders that are missing the design info or weight and volume values needed to convert to a source production unit of measure.
- Material Supply – See totals for component materials needed to meet expected demand.
First, select a 1 Week or 6 Week timeframe. Next, click in the date field to select the start date. The end date will select automatically.
(Material Demand view only) Click the Show Materials button to display or hide materials and their quantities under each place.
Enter a term into the Search field to find a location or material. The list filters as you type.
Click the Filters button at the top right of the page to access the Filter menu.
Inside the Filters menu, select one or more filters (Place Business Unit, Place Category, Place Name, etc.) and then instances for each.
For example, if you select the "Place Business Unit” filter and add a business unit, the material production view will only show the places within that business unit and any associated orders for the returned source places. Applied filters will appear on the view and can be removed by clicking the Clear Filters button or by removing each filter individually.
Filters will persist by user across sessions.
Working with Places that Produce Materials
Use Order view to see material orders for a specific location. Select an order to see its details. Depending on your permissions, you can also copy, edit, or delete an order.
View the total demand for all materials at a location, or see materials individually by turning on the Show Materials toggle.
Material supply is calculated based on material demand and the designs associated with those orders.
Material weight or volume has not been set
This is due to a material not having a unit weight or unit volume set which allows the system to total quantities by place.
Resolution
Edit the material properties to set the “Unit Weight” or “Unit Volume” and “Unit Weight UM” or “Unit Volume UM” values.
Place is over capacity
This is when the hourly production rate exceeds the capacity rate set at the location.
Resolution
Adjust material orders assigned to that location to either be produced at a different location, start at a different time or adjust the duration.
Resolving Design Conflicts
When a material order has a design conflict, a warning icon will appear next to its location or material on the Material Production page. This conflict is due to material orders having missing or invalid designs needed to calculate material demand and supply.
A design conflict warning appears when a material order meets the following criteria:
- Order is for a material associated with one or more material designs AND
- Material Design field on the order is empty OR
- Material Design has a design that does not cover the dates of the order
The Design Conflicts view allows you to quickly identify and resolve material orders that have missing or invalid designs. The Design Conflicts view is launched from the Material Production page in any warning dialog that shows Orders have missing or invalid designs by clicking View Design Conflicts.
Design Conflicts View Glossary
Menu Options
- Source – The place associated with the material order's source. Click on the Source menu to see a list of available sources.
- Material – Materials with orders that have invalid designs.
List Columns
- Material – The type of material.
- Order For – The customer, job site, or place ordering the material.
- Design – Indicates the cause of the conflict: design is “Not set” or "Invalid.”
- Amount – The quantity of the material on the order.
- UM – The material's unit of measure.
Choose a design pane
- All / In Use – Use this toggle to show either all designs or only designs currently in use.
- Design – The name of the design.
- Expiration Date – The date when the design will become invalid.
- In the warning dialog, click View Design Conflicts to open the Design Conflicts view.
- In the list of conflicts, select the check box next to the order you want to resolve.
- Choose a design from the Choose a design panel. Confirm the changes when prompted to apply the updates.
- Use the < icon at the top left of the page to return to the Material Production page or choose another conflict from the list to resolve.