Use the True-up feature to make adjustments to reported values in B2W Track based on data from your accounting system. A true-up will adjust for differences that can accrue between reported values in Track and actuals from accounting; over time these differences can be significant. For example, labor rates used in Track are typically average hourly rates by labor type, while actual payroll rates vary for different employees of the same labor type.

True-up can be done on the following values:

  • Job Tracking Accounts (Production, Overhead, T&M) — True-up can be done for costs, T&M prices, labor and equipment hours, and produced quantities.
  • Job Estimate Items — True-up can be done for produced quantity.
  • Job Material Quantities — True up can be done for material quantities delivered and used.

True-up information and actions are found within the following tabs in Jobs:

Getting Started

To use the True-up feature, you must download, install, and configure the True-up import add-in. This add-in can be found on the Add Ins & Reports tab of the B2W Community Portal. You will find the associated help on the same page as the add-in. Use this file to help install and configure the add-in.

Set True-up Permissions

You can set permissions on the True-up feature so only certain security roles can view, edit, delete, and import true-up information.

  1. Click Setup > Security Roles.
  2. Click Edit on the Security Role View page.
  3. Under the Jobs section of the Security Role Edit page, use the check boxes and colored icons to select which true-up permissions you want the security role to have.
  4. Click Save.

For more help, see Security Role Permission Settings.

Run/Import a True-up

These functions require the CSV True-up Import add-in.

You can run or import a true-up from the Jobs listing page, the Activity tab, the Estimate Items page, and the Production Account page.

Jobs Listing Page

  1. Click the JOBS tab.
  2. Click Run a True-up at the top of the page.

Activity Tab

  1. Click the JOBS tab.
  2. Select a job from the jobs list.
  3. Click the Activity tab at the top of the page of the job you selected.
  4. Click Run a True-up.

Estimate Items Page

  1. Click the JOBS tab.
  2. Click the Estimate Items tab.
  3. Click on an Item ID.
  4. Click on True-up next to the Reported Quantity.

Production Account Page

  1. Click the JOBS tab.
  2. Click the Tracking Accounts tab.
  3. Click on a Tracking ID in the Job Production Accounts section.
  4. Click on True-up next to the Total Reported Quantity.

Troubleshooting

If the Run a True-up Wizard does not launch when you click Run a True-up, you need to download and install the B2W Operations Add-in Launcher. You can download the installation package for the installer from the True-up add-in page on the B2W Community Portal.

True-up Actions

Your ability to perform certain actions are based on your security role and permissions.

Add True-up Notes

You cannot import notes about a true-up, but you can add notes to an imported true-up. Follow these steps:

  1. Select a job from the Jobs listing page.
  2. Click the Activity tab.
  3. In the Activity section of the Activity tab, select a true-up link in the Activity ID column.
  4. In the Notes field toward the top of the page, click Edit Notes .
  5. Enter your notes and click Save.

To Add or Edit notes, you need View and Edit True-up security permissions.

Delete True-up
  1. Select a job from the Jobs page.
  2. Click the Activity tab.
  3. In the Activity section of the Activity tab, select a true-up link in the Activity ID column.
  4. At the top of the true-up details page, click Delete.

Only the most recent true-up can be deleted on a job.