Skip to main content

Setting up a Cost Billing Instruction

Modified: 6 Nov 2026 Jobpac Connect Equipment Help

This can be done from the Asset enquiry.

Select the Asset with the option Costing History.

???

Then Select Add Cost Instruction.

???

The Income GL account comes from the FACOST parameter. Then Costing details are added. These can be to more than one cost centre but must ad to 100%.

At EOM, the system picks up various costs associated with the Asset and cost them to the Job in the instruction

If FACBDP position 1 is set to N or not present, then the following costs are included in this transaction:

  • Depreciation
  • Amortisation
  • Finance Lease Charges
  • Finance Lease Interest
  • Finance Lease Payment

If FACBDP position 1 is set to Y, then the following costs are included in this transaction:

  • Depreciation
  • Finance Lease Charges
  • Finance Lease Interest
  • Finance Lease Payment

If FACBIL position 1 is set to Y, then cost billing applies to all assets.

If FACBIL position 1 is set to N, then Plant assets are excluded from the Cost Billing.

(Perhaps because the Hire rate is set to include these costs)

At EOM, when this Cost Billing occurs, there is a hierarchy that determines what costing is used:

  1. If Cost Billing Instruction exists, then the Cost Billing is used
  2. If Cost Billing does not exist, then the Cost Billing default is used