Adjusting the Contract period

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

Information on this screen is primarily from the Schedule screen in Job Maintenance.

Updates need to be done in the Schedule screen, and are then displayed here.

???

Only days entered in the field headed Expected E.O.T. Award are included when recalculating the revised project Contract period.

The Link Forecast Date option will determine if the Work in Hand date is updated from the Forecast Completion date and vice versa.