After Job Costing is Rolled over

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

After Job Costing is Rolled over.

General

  1. Update the completion dates in Job setup
  2. Review and transfer all appropriate variations
  3. Select Contract Valuation from BFM menu and Select project (displays the Project Summary screen).

Prepare Cost Accruals

  1. Select Costs, (displays Cost Reconciliation screen)
  2. Select a cost type row, select All Cost Centres, then select Accrual/Adjust, and record any accruals for each cost centre.
  3. Return to Summary Screen.

Prepare Cost Forecast.

  1. Select Costs (displays Cost Reconciliation screen)
  2. Select a cost type row, and select All Cost Centres
  3. Select Project Managers Worksheet and prepare a forecast cost to complete for all cost centres. Return to Summary Screen.

Review Performance Surplus/Shortfall

  1. Select Turnover, and review Performance Surplus/Shortfall.

Review Margin

  1. Review margin to date and Margin this year.

Prepare Monthly WIH Forecast, and Monthly Cash Flow Forecast.

  1. Update Work in Hand Date. This is the date that major costs for the project will have been processed by, usually one month after practical completion. Update Financial Completion Date. This is the date after which no payments or receipts will be received.
  2. Select Work in Hand
  3. Forecast project costs month by month to end of project (i.e. Forecast completion date). Forecast payments and receipts to end of project (i.e. Financial Completion Date).
  4. Return to Summary screen.

Report and Review

  1. Run BFM Project Summary Report and Cost Comparison and Forecast Report and review.
  2. Revise as appropriate.
  3. Lock project (you will only be able to do this if step 14 to 16 are done).
Submit