The Secured and Unsecured Works components of the BFM can be configured to use predefined Profit Taking Thresholds when calculating JTD Margin Earned and forecasting margin take-up within the Work In Hand (WIH) screens.
The BFM allows profit taking thresholds to be defined at:
- Project Type level
- Project group level
- By exception, as a project specific threshold value
To access Business Forecasting>BFM Utilities>Project Types Maintenance
The makeup of the cost type components to be used when calculating the Cost Completion percentage, can also be optionally defined using the Profit Taking Threshold maintenance program. If no specific Cost Types are defined, then all Cost Types defined for the Work Id will be used in the calculation.
When a profit taking threshold is applied to a project job to date margin calculation, the deferred margin (Profit Taking Effect) is shown as a Turnover component within Contract Valuation.
| Field Name | Description |
|---|---|
| PTT% |
Profit taking Threshold percentage is the completion percentage threshold to be achieved, before margin release can occur. The BFM system parameter Profit Taking Threshold Method will determine if the full held margin is released or the margin take up will be prorated over the remaining project timeline. |
| <PTT% |
This percentage allows for partial release of deferred margin prior to achieving the defined completion threshold. i.e. if this 10%, then 10% of the deferred margin will be released up to meeting the threshold. |
| Reserve Hold % |
Defines the percentage of Forecast Final Margin that should continue to be withheld after the completion percentage has exceeded the defined PTT%.i.e if this is 5%, then 5% of the original withheld margin will continue to be withheld. |
| Reserve Release % |
The completion percentage threshold that needs to be achieved prior to release of the margin reserve. i.e if this 90%, then the 5% withheld margin from example above will be released when the project is 90% cost Complete. |
To override the Project Type based rules for specific projects e.g. high risk projects, the BFM Project Profit Taking Threshold maintenance program can be used.
To access Business Forecasting>BFM Utilities>Group PTT and Default DCV
The same rules apply as above for PTT.
The Unbalancing default for projects with a specific Group Code can also be set in this screen. If Group codes are not used, a default should be set for blank Group Code.
The default for Profit Taking Threshold, i.e. Immediate Take-up or Normal can also be set for Project Groups in this screen.
To access Business Forecasting>BFM Utilities>Project Profit Thresholds
The same project type, PTT configuration options are available but now operate by exception for each of the projects defined in the above panel.