Completion % Analysis

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

The percentage completion analysis is a comparative summary of a project’s current and prior period position up to the displayed As at date.

The As at date is recorded when Job costing end-of-month processing is completed.

  • Time (Cont): the % time elapsed from Contract Commence date up to the As at date, relative to the Contract Current Completion date.
  • Time: the % time elapsed from Contract Commencement Date up to the As at date, relative to the Target Completion date.
  • Revenue: the percentage of Billings relative to the Forecast Final Contract Sum (FFCS).
  • Costs: the percentage of cost expended to date (Cost of Work in Progress) relative to Forecast Final Costs (FFC).
  • Margin: the percentage of Margin Earned/Recognised to Date relative to Forecast Final Margin.