The percentage completion analysis is a comparative summary of a project’s current and prior period position up to the displayed As at date.
The As at date is recorded when Job costing end-of-month processing is completed.
- Time (Cont): the % time elapsed from Contract Commence date up to the As at date, relative to the Contract Current Completion date.
- Time: the % time elapsed from Contract Commencement Date up to the As at date, relative to the Target Completion date.
- Revenue: the percentage of Billings relative to the Forecast Final Contract Sum (FFCS).
- Costs: the percentage of cost expended to date (Cost of Work in Progress) relative to Forecast Final Costs (FFC).
- Margin: the percentage of Margin Earned/Recognised to Date relative to Forecast Final Margin.