The Contract Valuation Summary screen provides a concise financial summary of a project’s position and performance for the measurement period selected.
Access and navigational control is provided for the related supporting schedules by selecting from the options on the Actions menu.
The BFM Contract Valuation Summary screen is shown below:

As at field
This field displays the accounting period you select, for example ‘NOV21’. The default value is the current BFM period is active.
To display historical valuation information for other accounting periods, select the red arrow to add/decrease the period and year. Or simply type over the As at period displayed and input the required period value in MMMYY.
Job field
Select the red arrow
to go to the next job. Select
to go to the first job in the
list. Select
to go the last job in the
list.
The financial impact of related Contract Valuation adjustments entered and recorded in the supporting schedules are always updated in the Contract Valuation Worksheet and can be reviewed at any time using the Project Summary screen.
Columns and Rows displayed on the Project Summary grid will alter depending upon the selected TAB (Original Contract Value (OCV), Forecast Movement (FM), Year To Date (YTD), Work in Hand (WIH), Contingency (CON)).
|
Columns |
Description |
TAB |
|---|---|---|
|
Original Contract Values |
Revenue, Budget, Margin at the time of finalising budgets |
OCV, CON |
|
Current Contract Values |
Current Contract values. Difference from Original will be transferred head contract variations. |
All |
|
In Stage Position |
Last period, movement this period, and project to date. |
OCV, FM |
|
Movement, Year to Date, Project to Date |
YTD, WIH |
|
|
Completion Forecasts |
Forecast Final Revenue, Costs, Margin, This Period, and Last Period. |
ALL |
|
WIH |
Work in Hand values. WIH = Forecast Final Cost – Cost to Date |
WIH |
|
Rows |
Description |
TAB |
|
Gross Revenue |
For Contracts Values this is Original and Current Contract Sums For In Stage values this is Progress Claims plus Sundry Invoices, plus Sales Journals For Forecast Values this is Forecast Final Revenue |
|
|
Turnover |
This is represented as the sum of Cost of Work in Progress (CWIP) and Margin Earned to Date (Gross Margin). |
|
|
Costs |
For Contracts Values this is Original and Current Budgets For In Stage values this is Cost of Work in Progress For Forecast Values this is Forecast Final Cost |
|
|
Gross Margin |
For Contracts Values this is Original and Current Margin For In Stage values this is Revenue – Cost + Work in Progress For Forecast Values this is Forecast Final Revenue – Forecast Final Cost |
|
|
Gross Margin % |
The percentage of Gross Margin relative to Turnover (not cost) |
|
|
Corp Allocation |
The allocation of user defined non project (overhead) costs based on percentage of project turnover to total turnover. |
Only if Corp Allocation turned on. |
|
Operating Margin |
The net of Gross Margin and Corp Allocation. |
Only if Corp Allocation turned on |
|
Operating Margin % |
The percentage of Operation Margin relative to Turnover. |
Only if Corp Allocation turned on |
|
AFM |
Approved Final Margin calculated as Gross Margin including R&O take-up. |
Only if R&O take-up used |
|
AFM % |
The percentage of AFM relative to Turnover. |
|
|
Margin Variance |
The proportional movement in Forecast Final Contract Sum relative to Original Contract Sum, applied to Original Contract Margin net of Forecast Final Margin. Margin Variance = FFM - ((Forecast Turnover/Original Turnover)*Original Margin) |