Contract Valuation Summary

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

The Contract Valuation Summary screen provides a concise financial summary of a project’s position and performance for the measurement period selected.

Access and navigational control is provided for the related supporting schedules by selecting from the options on the Actions menu.

The BFM Contract Valuation Summary screen is shown below:

???

As at field

This field displays the accounting period you select, for example ‘NOV21’. The default value is the current BFM period is active.

To display historical valuation information for other accounting periods, select the red arrow to add/decrease the period and year. Or simply type over the As at period displayed and input the required period value in MMMYY.

Job field

Select the red arrow ??? to go to the next job. Select ??? to go to the first job in the list. Select ??? to go the last job in the list.

The financial impact of related Contract Valuation adjustments entered and recorded in the supporting schedules are always updated in the Contract Valuation Worksheet and can be reviewed at any time using the Project Summary screen.

Columns and Rows displayed on the Project Summary grid will alter depending upon the selected TAB (Original Contract Value (OCV), Forecast Movement (FM), Year To Date (YTD), Work in Hand (WIH), Contingency (CON)).

Columns

Description

TAB

Original Contract Values

Revenue, Budget, Margin at the time of finalising budgets

OCV, CON

Current Contract Values

Current Contract values. Difference from Original will be transferred head contract variations.

All

In Stage Position

Last period, movement this period, and project to date.

OCV, FM

Movement, Year to Date, Project to Date

YTD, WIH

Completion Forecasts

Forecast Final Revenue, Costs, Margin, This Period, and Last Period.

ALL

WIH

Work in Hand values. WIH = Forecast Final Cost – Cost to Date

WIH

Rows

Description

TAB

Gross Revenue

For Contracts Values this is Original and Current Contract Sums

For In Stage values this is Progress Claims plus Sundry Invoices, plus Sales Journals

For Forecast Values this is Forecast Final Revenue

Turnover

This is represented as the sum of Cost of Work in Progress (CWIP) and Margin Earned to Date (Gross Margin).

Costs

For Contracts Values this is Original and Current Budgets

For In Stage values this is Cost of Work in Progress

For Forecast Values this is Forecast Final Cost

Gross Margin

For Contracts Values this is Original and Current Margin

For In Stage values this is Revenue – Cost + Work in Progress

For Forecast Values this is Forecast Final Revenue – Forecast Final Cost

Gross Margin %

The percentage of Gross Margin relative to Turnover (not cost)

Corp Allocation

The allocation of user defined non project (overhead) costs based on percentage of project turnover to total turnover.

Only if Corp Allocation turned on.

Operating Margin

The net of Gross Margin and Corp Allocation.

Only if Corp Allocation turned on

Operating Margin %

The percentage of Operation Margin relative to Turnover.

Only if Corp Allocation turned on

AFM

Approved Final Margin calculated as Gross Margin including R&O take-up.

Only if R&O take-up used

AFM %

The percentage of AFM relative to Turnover.

Margin Variance

The proportional movement in Forecast Final Contract Sum relative to Original Contract Sum, applied to Original Contract Margin net of Forecast Final Margin.

Margin Variance =

FFM - ((Forecast Turnover/Original Turnover)*Original Margin)

Note: AFM Margin will only be displayed for projects where the R&O take-up option has been activated.
Submit