A number of organisations have accounting policies in place which require projects to defer recognition of CWIP relating to ‘Unfixed Materials’ until those materials have been incorporated into the permanent project works.
This treatment is commonly referred to as Material on / off Site (MOS) cost valuation.
The Contract Valuation Worksheet MOS facility allows for the entry of MOS values.
The MOS values should always be input as positive values within the Contract Valuation Worksheet. They will be treated as negative accruals automatically, i.e. reduction in cost.
These are entered in the same way as for Accrual/Adjustments.
Note: Only those cost types nominated in the BFM System Parameter can
be used for MOS accruals.