About rarely used BFM Project Types.
Duration (D)
The JTD Margin is calculated using time percentage completion i.e. actual time elapsed since project commencement over total project duration (end point defined by Target Completion date) applied to FFM.
If a Loss Job is forecast (negative Forecast Final Margin), then 100% of the loss will be recognised irrespective of the level of In-stage completion achieved.
Original Contract values and variation and scope changes are included in Order Intake Analysis.
Formwork Systems (F)
The JTD Margin is calculated using time percentage completion i.e. actual time elapsed since project commencement over total project duration (end point defined by Target Completion date) applied to FFM.
The Project profit Taking Threshold table is used:
- To defer profit recognition until the formwork system is delivered to site.
- Proportionally release profit over the ‘remaining’ project timeline after delivery.
The Unbalancing schedule is automatically updated with Time percentage completion to calculate income in advance.
If a Loss Job is forecast (negative Forecast Final Margin), then 100% of the loss will be recognised irrespective of the level of In-stage completion achieved.
Original Contract values and variation and scope changes are included in Order Intake Analysis.
Minor Works (M)
The JTD Margin is calculated using the percentage of Cost Completion applied to the FFM, together with automatic prorata allocation of remaining Work in Hand and Cash flow values across the remaining project timeline (controlled by the Forecast and Financial Completion dates, respectively).
Internal (I)
When internal interest on working capital, overhead, related party projects allocations or plant under/over absorptions are re-allocated back to project operations, a special internal project can be used within the BFM for differentiation of the makeup of project Gross Margin results.
The values recorded in the ‘Internal’ projects are subsequently reported as a separate reporting line in the Secured Works analysis in the Business Trading Summary (BTS).
Original Contract values and variation and scope changes are included in Order Intake Analysis.
Settlement (S)
The recognition of JTD Margin relating to a specific property sale and settlement milestone can be controlled in BFM using project type ‘S’.
If the project status in Job Maintenance is updated to reflect ‘settlement’ for a Property Development job, the BFM will release and recognise 100% of the Project Margin (FFM) and generate the required accounting entries to move the full cost of WIP for the project from Balance Sheet WIP, to the Profit/Loss statement.
Original Contract values and variation and scope changes are included in Order Intake Analysis.
Development (A)
The JTD Margin is calculated based on using a combination of the percentage of Sales Revenue received, together with the percentage of Cost Completion as at the review period, subject to:
- The definition of the makeup of the cost components used to calculate the Cost Completion percentage.
- Any Profit Taking Threshold defined (see Profit Taking Threshold Maintenance).
If a Loss Job is forecast (negative Forecast Final Margin (FFM), 100% of the loss is recognised irrespective of the level of In-stage completion achieved.
Original Contract values and variation and scope changes are included in Order Intake Analysis.
Contingency (T)
When a project is created within Jobpac to management income and/or cost contingencies, a special Contingency project type can be linked to the project to provide flexibility in managing Work in Hand distributions and margin effects during the Contract Valuation process.
The JTD Margin for Contingency job is again calculated as the difference between JTD Turnover (assumed to be manual Under / Over claim & WIP entries) and Cost of Work in Progress (CWIP – assumed to be manual cost accruals / adjustments).
Original Contract values and variation and scope changes are included in Order Intake Analysis.
Pending Award (W)
This project type automatically calculates a balancing Work in Progress value as a component of the Turnover analysis to offset the value of Cost of Work in Progress. It is used for projects which have not yet been formally awarded but have been established in Jobpac and have costs booked or incurred. This is to ensure that no Profit and Loss (JTD Margin) impact occurs.