End of Month Process

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

When Job Cost is rolled into the next month, any forecast that is in progress or is locked will be updated with the committed costs and actual costs at the time of rollover.

So that the Forecast Final Cost (FFC) is not changed, an equivalent change is made to the Forecast Costs to Complete (FCC), so that

For PMW formula E Committed Cost + FCC = FFC

For PMW Formula H CWIP + FCC = FFC.

Any change made to the FCC will be supported by a Project Managers Worksheet (PMW) entry representing the difference between the existing PMW entries and the revised value of the FCC. This entry will not be retained in the forward period.

Any WIP changes can continue to be made, i.e. WIP, Under/Over Claims.

When the Job cost rollover occurs, the WIH and cash forecast values for the forecast period will be replaced by the actual WIH and actual Cash values for that period. In order to preserve the total WIH and cash spread that was done during the forecast, the next forecast period for WIH and Cash will be adjusted by an equivalent amount.

If the Forecast was locked prior to the Job Cost Rollover, or a Super lock is in place for that project, then Accruals and Cost Transfers can continue to be made in the review period, however they will not impact the FFC. If an accrual or cost transfer would result in a change to FFC, then an equivalent change is made to FCC so the FFC is not impacted. Any accrual will also adjust the WIH value for that month, so an equivalent adjustment will be made to the next WIH period to maintain the same overall total for WIH.

If the forecast is unlocked, then the project returns to the normal process rules for Contract Valuation.