Skip to main content

Locking the Forecast

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

Ticking the ‘Forecast Locked’ will check that no WIH or Cash Forecast unallocated amounts exist.

If they do then an error message will be displayed.

‘BFM 1008 Project cannot be locked, as unallocated WIH/Cash values exist.

The UDF fields are not checked in this locking process. These can be entered at any time, and mandatory UDFs are only checked when the BFM Project Lock is used.

Once a Forecast is locked, no changes can be made that would change the Forecast Final cost or Forecast Final Revenue.

This includes:

  • Forecast Insurance Claims
  • Forecast Sundry Income
  • Scope changes
  • LDs and Bonuses
  • Price Fluctuations
  • Forecast Cost to Complete
  • Project Managers Worksheet (PMW) Entries
  • Risk and Opportunities
  • Work in Hand Forecasting
  • Cash Forecasting.

The following items can be changed after the Forecast is Locked, and before the BFM lock is applied to the project:

  • Unapproved Variations Claimed, Certified, Received to Date
  • Over/Under Claims
  • WIP
  • Cost Transfers
  • Cost Accruals, MOS, UVTM

Any changes after the forecast is locked by Cost Transfers, or by Cost Accruals, MOS, or UVTM must not impact the FFC for that cost centre, and an equivalent adjustment will be made to the FCC, including a supporting PMW transaction, so that the FFC will not change.

If more changes are required after the Project is locked, then the ‘Forecast Locked’ box can be unticked. This is subject to the BFM Locking level of the user.

The BFM ‘lock’ flag will remain greyed out, but will be available to use to lock the project after Job Costing Rollover.