If the PREFST parameter is set to Y, new options will be displayed at the top of the BFM Contract Valuation Summary Screen for Child Projects, Standard Projects, and Parent Projects.
New options will be displayed at the top of the BFM Contract Valuation Summary Screen for Child Projects, Standard Projects, and Parent Projects.

The Default position for Snapshot Type is None.
Other options are:
Current Forecast in Progress Based on a Snapshot of Current Data
Last Month Forecast in Progress Based on Snapshot of last Month position, i.e. that of the BFM history for the previous period.
Ticking either of these boxes will start the forecast process. Either the current set of data for that project or the last history data for the project will be copied to a set of forecasting tables, which will be used as a basis for the forecast. Any cost or revenue transactions after that time will not update these ‘copy’ tables. When the copy of the appropriate records has been done, the Date Started and Userid will be populated. This will signify to the user that the Forecast can now be started.

The default position for Forecast Lock is NOT ticked. When the Forecast is finished this box is ticked and the Userid and Date is populated. This will then prevent any further changes being done to the cash forecast.
For Parent Projects, the three options for Snapshot type will be greyed out. The Date Started will be the Date Started of the first Child Forecast.
When all Child projects are locked, the Parent can be locked.
The following changes can be done at Project level as part of this Forecast.
- Set WIH and Cash Flow Dates
- Changing Project Type (if user has access)
- Text for the period can be entered
- KPIs can be entered
- Revenue Summary screen. Nominated Subcontractor Amounts, Forecast Insurance Claims, and Forecast Sundry Income.
- Contract Works can be entered
- Variation Take-up (Variations can be transferred while this forecast is in progress, however they will not update the ‘Copy’ Files.
- Over/Under Claims
- Work in Progress
- Duration Screen, date update options, including Target date.
- Liquidated Damages
- Price Fluctuations
- Unapproved Variations Claimed, Certified, Received to Date
- Work in Hand and Cash forecast spread
- Entering KPIs
- Entering Text for Standard projects or Parent projects
- Risk and Opportunities.
Variation Transfers during the forecast Period will NOT update the current contract value of Forecast revenue or budget for the Forecasting snapshot. They WILL update the current file values.
The following changes can be done at Cost Centre level as part of this Forecast.
- Entry of Proposed FCC at cost centre level
- Entry of Project Managers Worksheet (PMW) entries
- Cost Accruals, MOS, and UVTW. These cannot be posted during the forecast period as no forward period records exist. They can only be posted after Job Cost Rollover in the Review Period.
- Cost Transfers. These can be posted during the forecast Period.
Any changes to the FCC during the Forecast need to be reflected in the ‘Current’ Files. If the FCC changes by 50, then this incremental change needs to be made to the FCC in the ‘Current’ Files, with corresponding changes to FFC, and Gain/Loss. This is to preserve the forecasting changes for the next period, when job costing is rolled.
Any new cost centres that are established during the Forecast process, either before or after the Forecast is locked, will also appear in the forecasting set of data, but with zero committed cost and actual costs. These cost centres can be forecast if required.
Any cost centres that are deleted during the Forecast process (standard deletion rules apply), either before or after the Forecast is locked, will also be deleted in the forecasting set of data.