Treatment of Parent Projects

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

Once any child of the Parent has commenced a forecast, then the Parent Start Date will be populated.

Users cannot lock the Forecast of the Parent Project until all the Children projects are locked.

Once a Parent Project is locked for Forecast, then a Child Project cannot be unlocked for Forecast.

If a new Child Project is created after the Parent Project has been locked, then this project will be copied to the ‘Copy’ Files with zero values for all numeric fields. This will enable any costs that update this new project to be included in the Project to Date costs at the end of the month for both the child and parent project. It will also have the Forecast Status ticked and the Snapshot Type set to Current. The userid of the person who locked the Parent will be used.

The parent project will continue to be the summary of all the children, independent of the forecasting status of the children.