Contract Works Schedule

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

The Contract Works screen is designed to provide a data entry maintenance capability for authorised users to maintain specific project Forecast Revenue elements not supported within Jobpac.

In summary, project ‘scope’ changes may be recorded to adjust FFCS when the related ‘scope’ change has not been processed through the Jobpac Variation module or within the Jobpac Item Maintenance program (Schedule of Rate Head Contracts). This easy to use screen has forecast maintenance capabilities to allow the user to assess and adjust the following Forecast Final Contract Sum (FFCS) elements:

  • Contract Works
  • Nominated Subcontracts
  • PC and Provisional Sums.

This schedule should rarely be used, as typically the Jobpac Variation module or Jobpac Item Maintenance programs are used to accurately maintain the current Contract Values and related Forecast values.

Select Contract Works from the options on the Actions menu.

The Contract Works screen can be updated by the direct input of values in the ‘Scope Changes’ column; the scope values typically represent the difference between the current Contract value recorded in Jobpac and the Final Forecast Contract Sum (FFCS) position expected.