The alternate R&O Detail – R&O Assessment screen can be accessed using the Next tab left menu option or by selecting the Take-up Tab in the R&O Details screen.
Fields for each issue
This table describes fields for each issue, including expected values and definitions.
|
Field Name |
Description |
|---|---|
|
Expected |
The project managers expected revenue or cost effect for this issue. The entry of Pessimistic and Optimistic values has also been provided but is not mandatory. This field is mandatory. |
|
Rev/Cst |
This flag defines whether the issue is Revenue or Cost related. This field is mandatory. |
|
R&O Assessment |
This is the realistic value assessed by an authorised commercial manager or executive relating to the issue recorded. |
|
R&O Take-up |
This is the take-up value included in the AFM. If the R&O Take-up value exceeds the R&O Assessment value, the assessment value will default to the take-up value. |
|
R&O Unsecured |
The difference between the assessment value and take-up value. |
|
Lnk2Var |
This flag defines whether the issue has been linked back one or more unapproved Variations recorded in the BFM Variation Register . |