Defining Turnover

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

In a number organisations Turnover is actually called Performance as it represents the true measurement of project achievement when measured against the project forecast final position.

As Project Type ‘N’ – Cost % Completion is the most commonly used standard in the industry, let’s review the following example of how Turnover of Job Performance is calculated

Turnover = CWIP plus Margin Earned

Where Margin Earned = Cost % Completion to Forecast Final Margin (FFM)

In this example, Turnover becomes a key project value to monitor and validate the accuracy of any project’s Forecast Final values by allowing comparison of what revenue (progress claim) position has been achieved to date.

At project Financial Completion:

  • Turnover is equal to Revenue, the total amount billed or payable to the Contractor
  • Costs are equal to the total amount paid or payable by the Contractor.
  • Gross Margin is equal to Turnover / Revenue minus Costs.

During the project lifecycle, the contracting organisation may have differing policies relating to project Gross Margin progressive release, some examples of which are shown below:

  • Straight line basis, based on Percentage Cost Completion
  • Straight line basis, based on Labour Percentage Cost Completion
  • Straight line basis, based on Percentage Revenue Completion
  • Profit Taking Thresholds based on either of the Cost or Revenue methods, but only after the Threshold or level of project progress has been achieved.

For ease of reference, and consistent with the mostly accepted industry and accounting standard, this manual will henceforth only refers to the Gross Margin determination using the Percentage Cost Completion method and total WIP is treated as an adjustment to Revenue.

To access the Turnover screen from the Contract Valuation Maintenance screen select Turnover from the options on the Actions menu.

???

The Turnover Schedule screen is automatically updated from the following related schedules and valuation components within the Worksheet:

  • Under/Over Claims Schedule
  • Work in Progress
  • Effect of Unbalancing
  • Profit Taking Effect
  • Future Loss Provision
  • Performance Surplus/Shortfall.

On review of the Turnover Schedule screen, the user can see a structured, quantified analysis of all of the above components that make up turnover.

The BFM Contract Valuation Worksheet does not simply classify the mathematical difference between Turnover and Revenue as total Work in Progress value.

The BFM encourages full assessment and measurement of all factors that substantiate this difference using the available supporting Schedules, with the resulting balancing item (Performance Surplus/Shortfall), effectively representing a key project indicator to monitor Job to Date performance relative to the defined Forecast Final Margin.