This is automatically calculated by Jobpac using the WKID or Project setting for withholding margin until a certain % Cost Complete is reached.
If a company has a policy of not declaring Profit on a straight line basis, then there has to be a component of To Date Performance deferred until the defined Profit Taking Threshold has been achieved at a later point in time.
The PTE calculation is quite straightforward, the example below uses a 20% Profit Taking Threshold (PTT %) applicable (see BFM System Administration) for the project with JTD Gross Margin recognition being based on Cost % completion and deferred profits released proportionally over the remaining project life.
The resultant JTD Gross Margin (Margin Earned) and PTE values being calculated as follows:
JTD Gross Margin = Forecast Final Margin * (Cost % Completion – PTT % / 100
– PTT%)
PTE = JTD Gross Margin – (Forecast Final Margin * Cost % Completion /
100)
When the work id configuration settings are set to fully release deferred profit when the defined PTT% progress milestone has been achieved (see BFM System Administration) the JTD Gross Margin calculation reverts to
JTD Gross Margin = Forecast Final Margin * (Cost % Completion /
100)