When a Project loss is forecast, Australian Accounting standards require that such loss is fully recognised at the time of identification.
In the Contract Valuation Worksheet a loss job effectively creates a ‘Provision for Future Losses’, for the as yet ‘Unexecuted’ or remaining portion of the project.
The ‘Provision for Future Losses’ (FLP) is calculated as follows:
JTD FLP = Forecast Final Margin * (100 - Cost % Completion / 100)