In the Construction and Engineering industry many projects are deliberately ‘front-end’ loaded, or have advances in their payments schedule as these help to generate early positive Cash flow for the project.
To not measure the Effect of Unbalancing and defer this element of revenue would otherwise distort other key project performance measurements and valuations and ultimately lead to inaccurate Balance Sheet presentation.
The BFM Contract Valuation Worksheet caters for this measurement, by providing a separate schedule where the effect of Unbalancing, or Client Early Payment, can be calculated.
Note: This option is generally turned off for most small to medium
construction companies.