Under claims and Over claims

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

An Under claim or an Over claim is defined as being one of the reconciling components when assessing the difference between revenue and turnover.

Within the BFM Contract Valuation Worksheet the measurement of Under claims or Over claims is in effect an assessment of the Revenue values (Project billings) that are recorded and reported as at the measurement period.

The measurement is in effect a substantiation of the value that the user believes will be certified and become immediately receivable from the client and become an element of the expected project cash flow within the next four to six weeks.

Depending on configuration, an Under/Over value can be entered directly into the Turnover screen as a summary value. This is configured by using the below option from the BFM system Parameter

???

If this is set to No, the user can Select Over/Under from the options on the Actions menu.

The assessment, measurement and recording of an Under claim or Over claim value are permitted by a direct data entry for the following revenue dissection types.

  • Contract Works
  • Materials On Site
  • Approved Variations
  • Unapproved Variations
  • Price Fluctuations
  • Nominated Subcontracts
  • Prime Cost and Provisional Sums
  • Insurance Claims
  • Sundry Income.

When the BFM Variation Register option is operational (see BFM System Administration) the assessment, measurement and recording of Under claims and Over claims relating to Variations can be processed directly at Variation detail level using the BFM Variation Details screen.

The revenue value claimed from the Client and processed as actual or accrued (Uncertified Progress Claim option) revenue within the Jobpac Job Costing and General Ledger modules is displayed within the JTD In Stage Position column within the Revenue Schedule in the Worksheet. However, these Revenue values may be up to one month behind, due to end of month processing timetables, delays in processing etc., so it becomes necessary to assess and value the difference between those actual JTD values recorded and what is expected to be certified as a Progress Claim value up to the end of the current measurement period.

These resulting Under/Over claim values are entered directly into this Schedule, against the related components, as positive (Under claim) or negative (Over claim) values respectively.