Updating the Unbalancing Schedule

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

In most Construction and Engineering projects, it is common for the tender mark-up for Gross Margin to be disproportionately weighted on parts of the payment schedule in the project's early phases.

To access Effect of Unbalancing from the Contract Valuation Maintenance screen, select Unbalanced from the options on the Actions menu.

In the screen below the function is turned off. (Option 2)

???

The project cost estimate values are therefore the only true measure as they represent the ‘Direct Cost Values’ (DCV), and invariably become the Project Cost budget.

To identify the element of Unbalancing, or ‘Front Loading’ included in assessed Revenue and Work in Progress to date, the BFM Unbalancing Schedule screen requires either entry or calculation of the ‘Direct Cost Value Earned’.

Four options are provided -

Option 1 - The DCV Earned value may be sourced externally to Jobpac and then entered directly into this Schedule by the user in either value or percentage terms.

Option 2 - The Unbalancing schedule is deactivated e.g., Small Order projects, Commercial Building projects.

Option 3 – The DCV Earned value is sourced and updated automatically from the Jobpac Earned Value module.

Option 4 - Direct input of an Unbalancing value (Front Loading or Advance Income assessment) with related DCV Earned value and percentage automatically calculated.

The recorded DCV % completion is automatically applied to Forecast Final Revenue (FFCS), giving a ‘theoretical’ Earned Revenue value which effectively represents what Job To Date Turnover should equate to if all project work schedule items were equally marked-up at the tender stage and the current progress claim position was directly valued or linked to costs expended as at the valuation period.

The ‘Effective Claimed Value’ is the sum of Revenue claimed, plus Under Claims, minus Over Claims, plus Work in Progress.

The ‘theoretical’ Earned Revenue value is compared to the ‘Effective Claimed Value’ to determine and display the Effect of Unbalancing value as the difference.

Note: The default for projects is Option 1. This may not be what is required and should be changed to Option 2 if the function is not required.

The default for projects with a specific Group Code can be set in the menu option Group PTT and Default DCV. If Group codes are not used, a default should be set for blank Group Code.

The default for Profit Taking Threshold, i.e., Immediate Take-up or Normal, can also be set for Project Groups.

???