Liquidated Damages and Bonuses

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

The BFM Liquidated Damages/Bonuses screen is a simple table that allows the user to maintain the Forecast Final Contract Sum (FFCS) to account for potential exposure to Liquidated Damages applied or to define the assessed opportunity to achieve a project bonus.

The BFM Liquidated Damages/Bonuses screen is a simple table that allows the user to maintain the Forecast Final Contract Sum (FFCS) to account for potential exposure to Liquidated Damages applied or to define the assessed opportunity to achieve a project bonus.

To access the Liquidated Damages/Bonuses screen from the Contract Valuation Maintenance screen, select Liquidated Damages from the options on the Actions menu.

This schedule is used to create or amend the forecast values relating to Liquidated Damages or Bonuses Earned by direct data entry of the amount in the relevant row under the Forecast at Completion column heading. Alternatively, you can enter the makeup of the amount by entering the quantity, unit of measure, and rate against either of these FFCS elements.

Important: Reductions in FFCS are entered as negative values and an increase in FFCS is entered as a positive value.

???

When the user selects OK, the FFCS value is recalculated within the BFM Contract Valuation Worksheet.

It is also possible to enter the claimed-to-date component relating to Bonuses Earned as a contra entry to the summary value initially displayed in the Claimed to Date column in this screen.