From the Variation Summary screen above, the Action option Variation Register will display a list of variations for the project.

The BFM Variation Register provides a comprehensive, time based analysis and valuation framework for all ‘Head Contract Variation’ elements recorded within Jobpac, including:

  • Take-up of Forecast Revenue Values (Unapproved Variations)
  • Measurement of Under/Over Claims
  • Measurement of Work in Progress
  • Optional recording or distribution of Variation claim values
???

There are a number of advanced options available to expedite the review and maintenance of project Head Contract Variation information recorded within the BFM Variation Register:

The BFM Variation Register screen has advanced filtering and tab selection options, for example:

  • Select the Approved Variations checkbox for example, and select OK to restrict the information displayed within the schedule to Unapproved Variations only.
  • View alternate TABS to review and optionally update maintain specific fields, such as Assessment, Claimed, Over/Under Claims, Margin, Margin & Reference and Take-up values.

To view or record additional text relating to an individual variation relating to status or commercial position etc. to support the forecast position taken, right-click and use the Text option.

To view an individual Variation record in detail, right-click and use the Select option.

???

Editable Field Names

Description

Claimed

Type in an amount for claimed value if any.

Status

Variation Status. Cannot be changed here

N = Not Submitted

W = Waiting for Approval

P = Approved in Principle

A = Approved

R = Rejected

D = Withdrawn.

Under /Over claim Values

The amount for under/over claim value if any.

Work in Progress

The amount for work in progress value if any.

Approval Expected/Achieved

Type in the month that Approval is expected. On approval the Approval month will be automatically recorded in this field. Information only.

Project Mgr Take-up

Type in the value for take-up as estimated by the Project Manager. Only for Unapproved Variations.

Managers Adjustment

An optional Commercial or Contract Manager’s adjustment can be recorded. Only for unapproved variations.

The project Forecast Final Contract Sum (FFCS) can be updated by

  1. Assessment and ‘take-up’ of forecast value against each unapproved Variation
  2. Linking unapproved, un-transferred variations to an R&O issue (see R&O Register) and recording a forecast ‘take-up’ value in the R&O register.

The use of each of the variation ‘take-up’ methods mentioned above is mutually exclusive and this is controlled by the configuration settings defined for the work id (see BFM System Administration and screen below).

???

If both the Recognise Unapproved Variations and Allow Direct R&O Take-up are ticked, this message appears.

When using option (a) above, the ‘take-up’ elements of Unapproved Variations are recorded within the following assessment fields:

  • Project Managers Take-up
  • Management Adjustment

The ‘Take-up’ values are entered as whole dollar values into the specific fields displayed within either the Variation Register Schedule or the Variation Detail screens. When the values are input and confirmed, and the ‘take-up’ percentage factors are calculated relative to the Variation ‘Expected Revenue’ values are recorded.

On exiting the Variation Register Schedule screen, the Variation Summary screen will refresh with the Unapproved Variation ‘take-up’ value automatically reflected as a component of the revised FFCS.

The complete FFCS analysis can also be reviewed within the Contract Valuation Revenue Schedule screen.

The BFM Variations Register Schedule and Detail selection screens also provide the capability to record an internal measurement for all Approved and Unapproved Variations for:

  • Under claims/Over claims
  • Work in Progress.

A number of additional informational and notational fields are displayed within BFM Variation Register screen to assist in the review and accurate time based management of all key project Variation details.

The use of the Jobpac Progress Claim module is optional and a number of clients choose to prepare their monthly progress claim outside of Jobpac and simply raise the progress claim in summary form in the Account Receivable module.

This creates a situation where the BFM cannot automatically retrieve the latest variation claim detail from within the Progress Claim module reliably, as the claim may or may not have been used this month.

The BFM Variation Register provides two options to record variation claim values for the review report

  • Manual recording and reconciliation of variation claim values into individual Variations in the BFM Variation Register.
  • Retrieval and ‘publishing’ of the latest variation claim values from the Progress Claim module.
Submit

Table of Contents