The Cash Flow Schedule screen is fully integrated within the Contract Valuation Worksheet, in order to provide a review and maintenance facility.
This allows the user to complete time-based allocation of the remaining Receipts and Payments over the remainder of the project and contract ‘Financial’ timeframe.
The outstanding Receipt and Payment values available for allocation within these screens within the remaining project financial period are calculated using the project forecast completion values less the values actually Received and Paid to date, as at the current measurement period.
The remaining time ‘window’ for the project, over which the remaining Receipt and Payment values are allocated is controlled by the Cash Flow Date field, as displayed and maintained within the Contract Valuation summary screen.

The Cash Flow review and allocation process commences with the selection and display of the Cash Flow Yearly Analysis screen, which dissects the project duration into financial year elements. The direct data entry of a value against either of the Receipts or Payments fields on a yearly analysis line is permitted when the year selected is either not yet completed or a future year.

Any prior financial year data can be viewed but not changed.
The objective of this screen is to allow the user to reforecast the expected Cash Flow values (O/S values) for the remaining years controlled by the project Financial Completion date.
Once this process is complete there should be no ‘Unallocated’ Cash Flow values recorded for the project.
Having allocated values over the remaining financial year records, it is then necessary for the user to allocate the forecast Receipts and Payments over the months within each remaining financial year. This is achieved by selecting the relevant year, right-clicking, and choosing Select and the 12 months dissected screen view displays.

The prior measurement periods are protected from data entry or change, with future periods available for user allocation of outstanding Receipts and Payments.
The user is required to manually enter and distribute the remaining outstanding values against each data entry row displayed to allocate the remaining values until there are no further ‘Unallocated’ values.
The Receipts and Payments values entered in these schedules are sourced and prepared external to the BFM using a combination of standard Jobpac reports and project-based spreadsheets.
The following utility options are available:
- Select the Clear Cash checkbox to initialize all forecast Receipt and Payment values recorded for the remaining periods in the financial year displayed.
- Or the user can directly enter the forecast receipt and payment values against each data entry capable month row displayed to ensure that no remaining ‘Unallocated’ values exist for that financial year, or alternatively after updating month cash forecasts then select the Accumulate Totals checkbox to update the financial year cash flow totals displayed.