About the Work in Hand Schedule

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

The Work in Hand Schedule screen is integrated within the Contract Valuation Worksheet to allow for time-based allocation of remaining project Turnover and Margin values over the remaining Contract execution period.

The WIH Turnover and Margin values available for allocation within the remaining timeframe of the project are calculated by the following:

WIH Cost = FFC – CWIP

WIH Revenue = FFR – Revenue to Date

WIH Margin = FFM – Margin to date

The remaining time "window" for the project, over which the remaining WIH values are allocated, is controlled by the Work in Hand Date, as displayed and maintained within the Contract Valuation summary screen.

Work in Hand Date display

The WIH review and allocation process commences with the selection and display of the WIH yearly analysis screen, which dissects the project duration into financial year elements with key project financial values and completion percentages.

The direct data entry of a value or percentage against either of the Turnover, Cost, or Margin fields (depending on Project Type) on a yearly analysis line is permitted when the year selected is either not yet completed or a future year.

Any prior financial year is displayed with historical data that can be viewed but not changed.

The objective of this screen is to allow the user to distribute the WIH values (O/S values) shown on the screen within the remaining financial years records that the project is forecast to be operating within. Once this process is complete, there should be no "Unallocated" values displayed on this screen (e.g., 80% complete at end of 2021/2022, and 100% complete in 2022/2023).

Allocating Values Over Remaining Financial Years

Yearly allocation screen

Having allocated values over the remaining financial year records, it is necessary for the user to allocate this forecast Turnover and Margin over the months within each remaining financial year. This is achieved by selecting the relevant year, right-clicking and choosing Select.

The 12-month dissected screen view displays with the prior measurement periods protected from data entry or change, and future periods available for user allocation of outstanding Turnover, Cost, and Margin.

Turnover, Margins, and Project Types

Turnover and Margin configuration
Note: The Turnover, Cost, and Margin are open to change depending on the configuration from the BFM System Parameter. These defaults can be overridden by the Project Type for the project.

BFM System Parameters Project Type Overrides

The user then allocates the outstanding Turnover, Cost, and Margin over future months for that year by using any of the following methods:

  • Select the Clear Totals checkbox to initialize all forecast values for the remaining periods in the financial year.
  • Select the Pro-rata Totals checkbox and then select OK. The unallocated values will be equally spread over the remaining months.
  • Directly enter values or completion percentages against each data entry capable month row.
  • Select the Accumulate Totals checkbox to update financial year totals to match manually entered values.
  • Configure the project type in BFM System Administration to automatically pro-rata the WIH values over the remaining months.
Important: There must be no "Unallocated" values remaining when an authorized user attempts to "lock" a project; otherwise, an error message displays, and reconciliation issues may occur in high-level BFM reports.