Skip to main content

Order Intake Analysis Calculation

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

There are two project elements that are recorded within BFM Order Intake Analysis

  1. Original Contract Value and Margin
  2. Variation or Scope Change Values and Margin (Forecast Final less Original Contract value)

Please note BFM Order Intake analysis uses project Original Margin percentage to calculate the (b) OI margin value above, so any project that does not have Original Contract values recorded will be excluded from Order Intake analysis, irrespective of the project type used.

Order Intake for a period is recognised as a change in Original Contract Value, or change in Transferred Variation value, or change in Scope for that month.