The JTD Margin is calculated using time percentage completion i.e. actual time elapsed since project commencement over total project duration.
If a Loss Job is forecast (negative Forecast Final Margin), then 100% of the loss will be recognised irrespective of the level of In-stage completion achieved.
Original Contract values and variation and scope changes are included in Order Intake Analysis.