When first implementing the BFM Contract Valuation module a common requirement is to allow client supplied JTD Margin and WIP Project Values to be loaded irrespective of percentage completion and forecast position.
The āLā ā Load on Values project type is supplied for this purpose.
There is no validation on Project Locking so unallocated Work in Hand values can exist.
The JTD Margin is calculated as the difference between JTD Turnover (JTD Revenue, Under/Over claim, WIP) and Cost of Work in Progress (CWIP).
This BFM Project type can be used if there is no requirement to calculate a WIP journal.
Original Contract values and variation and scope changes are included in Order Intake Analysis