Locking Unsecured Projects

Modified: 6 Nov 2026 Jobpac Connect Pre-Construction Help

The concept of hierarchical line management review of the Unsecured Project forecast is supported within the BFM.

As a Business Development, Commercial manager or designate completes all unsecured work updates, then a project can be locked to:

  • Prevent another user making further changes to the recorded position.

  • Provide a visual identification in the register that project has been assessed and updated.

While a project is locked, user access is restricted to enquiry mode only and no further maintenance can occur.

A locked project can only be unlocked by a user with an equivalent or higher unsecured project locking level authority, defined within their BFM user profile.

The edit capability to the lock option will only be enabled when a user has a lock level authority defined for their BFM user profile (see BFM System Administration).

When a project is locked, a locking audit stamp containing userid, date and time is recorded and displayed within Unsecured Works Maintenance for information purposes only.