Profit Taking Thresholds (PTT)

Modified: 6 Nov 2026 Jobpac Connect Pre-Construction Help

If a company has a policy of not declaring Profit on a straight line basis from project commencement, then a Profit Taking Threshold can be defined to defer margin recognition until the threshold has been reached.

If a default PTT has been defined for the Project Type in BFM System Maintenance, it will be recorded and used accordingly in Work in Hand (WIH) forecast projections.

If a Group Code is defined for a project, any default PTT defined for the Group code in BFM System Maintenance will override any Project Type default, and be used accordingly in Work in Hand (WIH) forecast projections.

The user can optionally override the PTT for a project within the Unsecured Works Maintenance screen, if a project specific risk assessment is to be applied.