Project Types define the supported profit recognition rules in Unsecured Works Maintenance used to calculate forecast margin for each period of the projects projected lifecycle.

???

Unsecured Project Maintenance – with Project Type ‘R’ defined

The project types supported within Unsecured Works Maintenance are:

  • Cost Collector (C): This can be used for projects where no revenue is processed and the project structure is used only to collect and manage costs. The expected Cost of Work in Progress (CWIP) that is forecast, is simply recorded as negative Gross Margin impact. The forecast at completion information relating to a cost collector is used to control the forecast projection of anticipated future costs and margin impact.

  • Internal (I): When internal interest on working capital, overhead, related party projects allocations or plant under/over absorptions are re-allocated back to project operations, a special internal project can be used within the BFM for differentiation of the makeup of project Gross Margin results.
    Note: The values recorded as ‘Internal’ projects are subsequently reported as a separate reporting line in the Unsecured Works analysis in the Business Trading Summary (BTS).
  • JTD Recognition (J): The forecast Margin is calculated as the difference between forecast Turnover and forecast Cost (CWIP).

  • Normal (N): The JTD Margin is calculated using the percentage of Cost Completion applied to the FFM with consideration of any Profit Taking Threshold defined (see Profit Taking Threshold Maintenance).

    Note: The forecasting of Loss Jobs (negative Forecast Final Margin) is not supported in Unsecured Works Maintenance.
  • Revenue (Billings) (R): The JTD Margin is calculated using the percentage of Revenue completion applied to the FFM, with consideration of any Profit Taking Threshold defined (see Profit Taking Threshold Maintenance).

  • Contingency (T): When an Unsecured project is created to manage income and/or cost contingencies, a special Contingency project type can be used to assist in managing Work in Hand distributions and controlling margin effects.

    The user can directly control the input of any combination of turnover, cost or margin to record the WIH allocation profile required.