Subcontracts

Modified: 6 Nov 2026 Jobpac Connect Accounts Payable Help

When you are registering a subcontract agreement, you can set up in such a way that the subcontractor supplies energy usage data whenever a progress claim is submitted. You can perform the following steps to set up a subcontract agreement:

  1. Expand the Finance menu in the left pane of the Jobpac Connect home screen.
  2. Expand the Subcontractors sub-menu.
  3. Click the Maintain Agreement option to display the Subcontract Maintenance screen.
  4. Click the search icon in the Job field to display the Job Search window.
  5. Select the required job and click the Select button in the Job Search window.
  6. Click the search icon in the Subcontractor field to display the Creditor Search- By Name window.
  7. Select the required creditor and click the Select button in the Creditor Search- By Name window.
  8. Click the search icon in the Agreement field to display the Subcontract Agreement Scan window.
  9. Select the required agreement and click the Select button at the bottom of the Subcontract Agreement Scan window.
  10. Select the This Subcontract must supply Energy Use data with each Progress Claim checkbox in the Subcontract Maintenance screen.
  11. Click the OK button at the top of the Subcontract Maintenance screen.