This section describes how to record supplier retentions and release of supplier retentions if held.
Generally this area is designed to record retentions held against materials suppliers.
Note: Under Subcontractors Agreements you can hold
a retention value against both the subcontractor and job. If Retention is applicable for a
supplier, it is strongly recommended that the SC Retention facility be used and not Creditor
Retention.
Select .
The supplier retention would have been held earlier via Post invoices (as described above).
When this held retention is ready for release (or partial release), select .
Enter the amount to be released for payment. This will create an invoice to pay to the supplier via the usual payment process.
Note: Reports are available under either by job or by supplier.