This section describes how to record supplier retentions and release of supplier retentions if held.

Generally this area is designed to record retentions held against materials suppliers.

Note: Under Subcontractors Agreements you can hold a retention value against both the subcontractor and job. If Retention is applicable for a supplier, it is strongly recommended that the SC Retention facility be used and not Creditor Retention.

Select Finance > Accounts Payable > Supplier Retentions.

The supplier retention would have been held earlier via Post invoices (as described above).

???

When this held retention is ready for release (or partial release), select Finance > Accounts Payable > Supplier Retentions > Release Supplier Rents.

???

Enter the amount to be released for payment. This will create an invoice to pay to the supplier via the usual payment process.

Note: Reports are available under Finance > Accounts Payable > Supplier Retentions either by job or by supplier.
Submit