Prepare a claim by entering claim amounts or quantities in the Progress Claim entry screens for Schedule Items and Variations.
- Prepare a claim (say Claim No 4) by entering claim amounts or quantities etc. in the Progress Claim entry screens, for Schedule Items and Variations.
- Enter any MOS Items via option 3.
- Print this claim as many times as required.
- When you are happy with the claim, print it, and mark as "Final" and "Yes – Post to accounts". This can be sent to the Client.
If the system is configured to establish an AR accrual claim with a status of 'P'.
- This Final Print will store Claim No 4 as History, and it will appear as an Uncertified, Un-accrued Progress Claim in Accounts Receivable (status ‘P’). The claim no will remain at 4. You can continue to change claim no 4 as often as required, while the Progress Claim in AR remains at the ‘P’ status. If you mark as "Final" and "Yes – Post to accounts" again this will store the revised claim and change the values in the AR ‘P’ record.
If the system is configured to establish an AR accrual claim with a status of 'U'
- This Final Print will store Claim No 4 as History, and it will appear as an Uncertified, Accrued Progress Claim in Accounts Receivable (status ‘U’). The claim no will change to 5. If you print Progress Claim no 4 again,and mark as "Final" and "Yes – Post to accounts". it will NOT update the accrued progress claim. The same changes apply if the Claim came into Accounts Receivable as ‘P’ status, and is then accrued in Accounts receivable and the Status changed to ‘U’.Note: It is the changing of the status to ‘U’ that updates the claim value.
- Once the Claim is at status 'U' in AR, it will show as recognised revenue against the project in Contract Valuation and all reports. The Progress Claim number then rolls over to 5 in your progress claim entry screen. The Claim 4 MOS entries will disappear from the MOS entry screen.
- Once the Claim has been accrued, and the Accrual is a ‘U’ status in AR, the accrued values can only be changed by using the Certified Claim Entry option in the Progress Claim menu. Any changes entered in this screen for both Contract Values and Variations, with update the posted accrual (ie Claim No 4) with an adjustment.
- If the Claim is then certified by the client at a different value than the one you sent to the client, the accrued value should again be changed by using the Certified Claim Entry option in the Progress Claim menu. This will update the Uncertified Claim No 4 in AR to the certified values. A revised Claim No 4 can be reprinted.
- In AR, the claim can then be certified by entering a certified date, and creating the invoice.
- Then you can 'Rollover' the claim, (Copy Current to Previous menu option), which copies Previous Claim Values to Current Claim Values. So the Previous values in the detailed claim tie in with the certified value. MOS entries should NOT be entered for the next claim until the Rollover has occurred. You can then start entering the next Claim.
- If, subsequently, the certified values need to be changed, then an adjustment can be done to that claim in the AR Progress Claim screen, providing the adjustment is done in the same month as the certified month. If the AR month has been rolled over, then a separate adjustment claim will need to be done.