Skip to main content

Cost Centres/Codes

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

Select Projects > Job Setup and Reports > Setup Cost Centres.

Budgets for SOR projects are not setup using Cost Centre maintenance, these are automatically calculated when budgets for each Schedule Item are entered in Item maintenance or when the Schedule is uploaded. However, the cost centres themselves must be setup using this screen if the project is being setup manually. To setup cost centres manually for SOR projects, select the Fast Entry option.

???

Cost Centres can be added after the last entry. Use ‘New Cost code’ in the Actions Menu.

Providing cost centres do not have budgets, they can be deleted from the screen below by replacing the X with a C and either press ENTER or click OK to update your changes. Multiple cost centres can be deleted at one time.

???
Note: When the Expert Estimator template upload is used and cost centres have not been defined the cost centres will be created during the upload process using descriptions from the template job nominated on the Job Maintenance “Type” TAB.
Submit