It is mandatory that every Schedule Item in a Schedule of Rates project is associated with a forecasting method.
General Explanation
This code will determine the relationship between the contracted quantity and the forecast final quantity for the Schedule Item. These codes are “Hard Coded” and cannot be changed, or new forecasting methods created.
These are setup using the following menu path. Only the descriptions can be changed.
Select Project .
These apply to all projects in a Workid, they are not project specific. All six must exist.
Business Rules
There are very specific business rules associated with these forecasting methods. These are described in the Item Maintenance section of this manual.
Standard Forecasting Methods
The available Forecasting Methods are outlined below. Additional methods are not supported without an enhancement to the base product.
| Method | Description |
|---|---|
| SC – Schedule Item Coupled |
Schedule of rates items where the Forecast Final Quantity (FFQ) is automatically kept by the system to be the same as the Current Contract Quantity, and vice versa. |
| SU – Schedule Item Uncoupled |
Schedule of rates items where the Current Contract Quantity is managed separately from the Forecast Final Quantity (FFQ). i.e. changes to the FFQ will not change the Current Contract Quantity, and vice versa. |
| LS – Lump Sum Item |
Schedule Items declared as a Lump Sum. The Current Contract Quantity is frozen at Budget finalisation time, and the user maintains the Forecast Final Quantity separately. |
| CM – Comment Item |
These are comment lines only, and have no impact on Contract Value or budget. Quantities or rates can be maintained against this type of item, but have no impact on contract. |
| RO – Rates Only |
These Schedule of Rates items will have a rate and may have a quantity and price, and have sub items to support the budget for the item. These items will NOT update the contract values, budgets, or margins, and are excluded from forecasting and may not appear on client schedules. |