Schedule of Rates Parameter for Preliminaries Management

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

Review the parameters for preliminaries management.

Description

Preliminaries recovery can be managed in different ways in Schedule of Rates projects. Sometimes preliminaries cost is included within the prices of each of the Schedule Items, and sometimes preliminaries are separate items on the schedule.

If preliminaries are separate items in the schedule, then they are setup as Schedule Items, and treated like any other item. If preliminaries budget is embedded as a % within each of the list of Schedule Items, then specific functionality exists to automatically calculate this budget.

A Schedule of Rates Parameter can be used to establish the business rules associated with this feature. This parameter is mandatory if overheads are contained within the Schedule Item rates, but does not have to be used if overheads are directly claimed from the client.

A % of the budget for each Schedule Item is defined, and as the budget for each item is entered ( or loaded from Expert Estimation template) into the system, the percentage is used to calculate a prelims budget amount, and this budget is accumulated a single nominated holding cost centre.

A normal set of preliminary cost centres should be setup for the project. These will initially have no budget. These preliminary cost centres will be linked by a number of prelims items with no budget and no price. All of these items will be setup with a defined Preliminaries Section defined in the parameter. Using item maintenance and these preliminaries items, sub items (resources) can be setup and related to preliminary cost centres. The budget for each of these items comes from the accumulated budget of the holding cost centre.

As Schedule Item quantities change, this will automatically increase or reduce the overall preliminaries budget. A user can then spread this additional budget across cost centres as required.

A flag is provided at the item level to exclude items from this contribution to the preliminaries budget if required. A flag is also available at the sub item level to exclude the selected sub item from the preliminaries budget contribution.

Setup SOR Parameter

To setup the SOR parameter use the following menu option Projects > Job Setup and Reports > Schedule of Rates > SOR Job Setup > Set SOR Parameter.

SOR Menu Path

To add a new parameter for a project, select Add. The following screen displays.

SOR Parameter Screen

Tip: If the project will be claiming preliminaries and overheads as part of the Claim Schedule, then only, the Workid, Job No and Variation Section field need to be entered.

Field

Description

Use one item for Preliminaries

This is ticked if only one item is to be used for all preliminary budgets. This is a carryover feature from release 7, and should not be used in R8, i.e. remain unticked.

Preliminary Section code.

This defines the Section of the project that will hold all of Preliminary items, including the nominated Preliminary Item Code which is used to hold the overhead budget made available via a component of each Schedule Item. Recommend that 9000 be used.

Preliminary Item Code

This defines the Item code which is used to hold the overhead budget made available via a component of each Schedule Item. Each Item must have a sequence number, and a system defined no of 999,999 is used for the Item. Suggest HOLDINGCP (holding contract prelims).

Preliminary sub item Line No.

Within each Schedule Item in the schedule, a sub item is automatically created to hold the overhead contribution of that Schedule Item. This field defines the line number that is used. It is usually set to 99,999 (the max number).

Preliminary Holding Cost Centre

This cost centre will hold budget that relates to the difference between the overhead budget provided from contributions from the Schedule Items, and the budget used for overhead items. This cost centre should not be used elsewhere on the project. Recommend 9996/M. Make sure this is setup in the Template project.

Default % for Budget Calculation

This is the default % of the total direct cost budget for a Schedule Item that goes to the “pool” of budget for overheads. This will be defaulted each time a new Schedule Item is created, but can be changed for that Schedule Item as required.

Fixed Prelims Under/Over Recovery spread Method.

When additional budget is made available via a remeasure of the schedule, the user has options as how to spread this additional budget to existing overhead budgets:

  • Allow spread by function key and no manual spread. Assigning this default option means the Actions option is used to automatically spread the additional budget to existing sub items in the prelims items, in the ratio of the current budget. No manual changes can be made to these budgets.
  • Allow spread by function key and allow manual spread. Assigning this default option means the Actions option is used to automatically spread the additional budget to existing sub items in the prelims items, in the ratio of the current budget, or the spread can be made by manual changes to these budgets.
  • No function Key available, only manual spread No automatic spread option available. The additional budget can only be spread manually.

Fixed Prelims Under/Over Recovery – Cost Centre

Individual overhead budget sub items can be marked to not receive any additional budget that may be made available. If the automatic spread method is used, the amount of the budget that would be allocated to those sub items marked to not receive additional budget, is placed in this nominated cost centre. This budget can be used as contingency or as a gain for the project. Recommend 9997/MT.

Variation section

The section that all variation Schedule Items are allocated to. This is the way the system determines the Schedule Item is part of a variation, and to apply the associated business rules for variation Schedule Items. Recommend 8000.
Note: This must be setup for all SOR projects.

Use one item for Variation Preliminaries.

This is ticked if only one item is to be used for all preliminary variation budgets. This is a carryover feature from release 7, and should not be used in R8, i.e. remain unticked.

Variation Preliminary Item Section code.

This defines the Section of the project that will hold all of the Variation Preliminary items, including the nominated Variation Preliminary Item Code which is used to hold the overhead budget made available via a component of each Variation Schedule Item. Recommend 9500.

Variation Preliminary Item Code.

This defines the Item code which is used to hold the Variation overhead budget made available via a component of each Variation Schedule Item. Each Item must have a sequence number, and a system defined no of 999,998 is used for the Item. Recommend HOLDINGVP (holding Variation prelims).

Variation Preliminary Sub item Line No.

Within each Variation Schedule Item in the schedule, a sub item is automatically created to hold the overhead contribution of that Variation Schedule Item. This field defines the line number that is used. It is usually set to 99,999 (the max number).

Variation Holding Cost Centre

This cost centre will hold budget that relates to the difference between the Variation overhead budget provided from contributions from the Schedule Items, and the budget used for Variation overhead items. This cost centre should not be used elsewhere on the project. Recommend 9998/MT.

Default % for Variation Budget Calculation

This is the default % of the total direct Variation cost budget for a Variation Schedule Item that goes to the “pool” of budget for Variation overheads. This will be defaulted each time a new Variation Schedule Item is created, but can be changed for that Schedule Item as required.

Fixed Prelims Under/Over Recovery spread Method.

When additional budget is made available via a remeasure of the Variation Schedule Items, the user has options as how to spread this additional budget to existing Variation overhead budgets:

  • Allow spread by function key and no manual spread. Assigning this default option means the Actions menu panel option is used to automatically spread the additional Variation budget to existing sub items in the Variation prelims items, in the ratio of the current budget. No manual changes can be made to these budgets.
  • Allow spread by function key and allow manual spread Assigning this default option means the Actions menu panel option is used to automatically spread the additional Variation budget to existing sub items in the Variation prelims items, in the ratio of the current budget, or the spread can be made by manual changes to these budgets.
  • No function Key available, only manual spread No automatic spread option available. The additional Variation budget can only be spread manually.

Fixed Prelims Under/Over Recovery – Cost Centre

Individual Variation overhead budget sub items can be marked to not receive any additional Variation budget that may be made available. If the automatic spread method is used, the amount of the budget that would be allocated to those sub items marked to not receive additional budget, is placed in this nominated cost centre. This budget can be used as contingency or as a gain for the project. Recommend 9999/MT.